Cleveland Bridge UK Ltd v Severfield - Rowen Structures Ltd [2012] EWHC 3652 (TCC) (21 December 2012)
The Court found that the June programme was not contractually binding, but the December programme reflected SRS's requirements and was accepted by conduct. CBUK was responsible for delays in fabrication and delivery, and SRS was entitled to recover reasonable acceleration and defect rectification costs as contra charges. CBUK was entitled to payment for substantiated variations but not for unsubstantiated claims or loss of productivity.
- Citation
- [2012] EWHC 3652 (TCC)
- Parties
- Claimant: Cleveland Bridge UK Limited; Defendant: Severfield – Rowen Structures Limited (formerly Severfield-Reeve Structures Limited)
- Jurisdiction
- England and Wales
- Judgment Date
- 21 December 2012
- Procedural Posture
- Commercial Construction Dispute / High Court Judgment
- Outcome
- Judgment for SRS with set-off of contra charges against sums due to CBUK.
- Legal Topics
- Delay in Performance, Variation Claims, Quality of Work, Contra Charges, Acceleration Costs
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Cleveland Bridge UK Limited
Claimant
Severfield – Rowen Structures Limited (formerly Severfield-Reeve Structures Limited)
Defendant
Procedural Posture
Commercial Construction Dispute / High Court Judgment
Legal Issues
- 1 Whether CBUK was contractually bound to the June or December programme
- 2 Whether delays in steelwork fabrication and delivery were caused by CBUK or SRS
- 3 Entitlement to payment for variations, including edge beam detail
Ratio Decidendi
The Court found that the June programme was not contractually binding, but the December programme reflected SRS's requirements and was accepted by conduct. CBUK was responsible for delays in fabrication and delivery, and SRS was entitled to recover reasonable acceleration and defect rectification costs as contra charges. CBUK was entitled to payment for substantiated variations but not for unsubstantiated claims or loss of productivity.
Court Disposition
Judgment for SRS with set-off of contra charges against sums due to CBUK.
Orders
- CBUK entitled to payment for substantiated variations and outstanding sums, less contra charges for delay, defects, and acceleration.
- SRS entitled to recover reasonable costs for nightshift erection squads, site staff, defect rectification, and disruption to metal decking installation.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment