GB Building Solutions Ltd v SFS Fire Services Ltd (t/a Central Fire Protection)
The definition of 'Practical Completion' in the schedule of modifications does not apply to section 6; instead, clause 2.20 applies for ascertaining the terminal date. The defendant gave a valid notice under clause 2.20.1, and since the claimant did not dissent, practical completion was deemed to have occurred...
Source-derived case information.
- Parties
- Claimant: GB Building Solutions Limited (in administration); Defendant: SFS Fire Services Limited (t/a Central Fire Protection)
- Jurisdiction
- England and Wales
- Judgment Date
- 25 May 2017
- Procedural Posture
- Civil (construction Dispute) / Judgment on Preliminary Issue
- Outcome
- Preliminary issue determined in favour of the claimant; the flood occurred after the terminal date.
- Legal Topics
- Contractual Interpretation, Practical Completion, Insurance Liability, Subcontractor Obligations, Specified Perils, Retention Release
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
GB Building Solutions Limited (in administration)
Claimant
SFS Fire Services Limited (t/a Central Fire Protection)
Defendant
Procedural Posture
Civil (construction Dispute) / Judgment on Preliminary Issue
Legal Issues
- 1 Whether the flood occurred before or after the terminal date (practical completion) under the subcontract
- 2 Whether the definition of 'Practical Completion' in the schedule of modifications applies to section 6 or clause 6.1
- 3 Whether a valid notice of practical completion was given under clause 2.20.1 and its effect
Ratio Decidendi
The definition of 'Practical Completion' in the schedule of modifications does not apply to section 6; instead, clause 2.20 applies for ascertaining the terminal date. The defendant gave a valid notice under clause 2.20.1, and since the claimant did not dissent, practical completion was deemed to have occurred before the flood. Even if actual completion was relevant, it had occurred by 9 December 2009. Therefore, the flood occurred after the terminal date, entitling the claimant to advance its claim.
Court Disposition
Preliminary issue determined in favour of the claimant; the flood occurred after the terminal date.
Orders
- It is declared that the flood occurred after the terminal date as defined by clause 2.20 of the subcontract.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment