Steria Ltd v Sigma Wireless Communications Ltd
Steria was entitled to the final payment as the delays were caused by Sigma/CAMP East's late provision of data and approvals, and the insistence on requirements outside the sub-contract scope. The liquidated damages clause was valid and not a penalty. The extension of time clause was a condition precedent, but Steria gave sufficient notice. Only one week of delay was attributable to Steria, entitling Sigma to one week's liquidated damages. Sigma's counterclaim for general damages failed due to the exclusive remedy provision and lack of causation.
- Parties
- Claimant: Steria Limited; Defendant: Sigma Wireless Communications Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 15 November 2007
- Procedural Posture
- Commercial Construction Dispute (sub Contract) / Final Judgment After Trial
- Outcome
- Judgment for claimant with set-off for one week of liquidated damages to defendant
- Legal Topics
- Liquidated Damages, Extension of Time, Penalty Clauses, Delay Claims, Sub Contractor Obligations, Notice Requirements
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Steria Limited
Claimant
Sigma Wireless Communications Limited
Defendant
Procedural Posture
Commercial Construction Dispute (sub Contract) / Final Judgment After Trial
Legal Issues
- 1 Whether the claimant is entitled to payment of the final tranche under the sub-contract
- 2 Whether the defendant is entitled to set off or counterclaim for liquidated or general damages for delay
- 3 Whether the liquidated damages clause is a penalty and thus unenforceable
Ratio Decidendi
Steria was entitled to the final payment as the delays were caused by Sigma/CAMP East's late provision of data and approvals, and the insistence on requirements outside the sub-contract scope. The liquidated damages clause was valid and not a penalty. The extension of time clause was a condition precedent, but Steria gave sufficient notice. Only one week of delay was attributable to Steria, entitling Sigma to one week's liquidated damages. Sigma's counterclaim for general damages failed due to the exclusive remedy provision and lack of causation.
Court Disposition
Judgment for claimant with set-off for one week of liquidated damages to defendant
Orders
- Steria to recover €153,786.89 less €7,688.37 (one week liquidated damages) for a net sum of €146,098.52
- Sigma's counterclaim for general damages dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment