Reginald Dean Hyde & Ors V Simple Skips Limited & Ors

Reginald Dean Hyde & Ors V Simple Skips Limited & Ors

The Second Defendant was contractually obliged to remove all waste from Mound 2 and the rear of the bays as at the date of the Settlement Agreement (8 December 2017), not limited by any specific volume, weight, or survey baseline. He failed to remove all such waste by 3 February 2021, leaving a substantial quantity...

Source-derived case information.

Parties
Claimant: Reginald Dean Hyde; Claimant: Nicholas Standeven; Claimant: ITR Global Limited; Defendant: Simple Skips Limited; Defendant: John Corney; Defendant: Keith Stiles
Jurisdiction
England and Wales
Judgment Date
24 March 2023
Procedural Posture
Civil / Trial of Preliminary Issues Following Consent Order in Enforcement Proceedings
Outcome
Claimants succeed on all four issues; Second Defendant found in breach of Settlement Agreement; Claimants entitled to enforce judgment for £300,000.
Legal Topics
Interpretation of Settlement Agreements, Enforcement of Consent Orders, Trespass to Land, Damages for Waste Disposal, Burden of Proof in Civil Cases
Contract Law Civil Procedure Property Law Interpretation of Settlement Agreements Enforcement of Consent Orders Trespass to Land Damages for Waste Disposal Burden of Proof in Civil Cases

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 6 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Reginald Dean Hyde

Claimant

Nicholas Standeven

Claimant

ITR Global Limited

Claimant

Simple Skips Limited

Defendant

John Corney

Defendant

Keith Stiles

Defendant

Procedural Posture

Civil / Trial of Preliminary Issues Following Consent Order in Enforcement Proceedings

  1. 1 What was the scope of the Second Defendant's obligation under the Settlement Agreement regarding waste removal?
  2. 2 Did the Second Defendant clear all waste from Mound 2 and the rear of the bays by 3 February 2021?
  3. 3 Was additional waste added to Mound 2 after the relevant date?

Ratio Decidendi

The Second Defendant was contractually obliged to remove all waste from Mound 2 and the rear of the bays as at the date of the Settlement Agreement (8 December 2017), not limited by any specific volume, weight, or survey baseline. He failed to remove all such waste by 3 February 2021, leaving a substantial quantity on site. There was no credible evidence that the Claimants added further waste after the relevant date. The obligation was not satisfied by reference to a particular number of lorry loads, tonnage, or volume, but required complete removal of all waste present at the relevant date.

Court Disposition

Claimants succeed on all four issues; Second Defendant found in breach of Settlement Agreement; Claimants entitled to enforce judgment for £300,000.

Orders

  • Counsel to agree form of order; court to hear submissions on consequential matters if necessary.