Solaria Energy UK Ltd v Department for Business, Energy And Industrial Strategy [2020] EWCA Civ 1625 (Hearing 4 November 2020)

Solaria Energy UK Ltd v Department for Business, Energy And Industrial Strategy [2020] EWCA Civ 1625 (Hearing 4 November 2020)

The Court of Appeal held that Solaria's sub-contract was a possession under A1P1 despite assignment restrictions, but the claim was statute-barred as it was brought nearly five years after the relevant act, and Solaria failed to demonstrate any equitable grounds to extend the limitation period under section 7(5)(b)...

Source-derived case information.

Citation
[2020] EWCA Civ 1625
Parties
Appellant: Solaria Energy UK Limited; Respondent: Department for Business, Energy and Industrial Strategy
Jurisdiction
England and Wales
Procedural Posture
Appeal / Court of Appeal Judgment on Appeal From High Court (tcc) Decision to Strike Out Claim
Outcome
Appeal dismissed
Legal Topics
Article 1 Protocol 1 ECHR (a1 P1), Limitation of Actions, Possessions Under Human Rights Act, Assignment of Contractual Rights, Summary Judgment/strike Out
Human Rights Law Contract Law Public Law Article 1 Protocol 1 ECHR (a1 P1) Limitation of Actions Possessions Under Human Rights Act Assignment of Contractual Rights Summary Judgment/strike Out

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 18 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Solaria Energy UK Limited

Appellant

Department for Business, Energy and Industrial Strategy

Respondent

Procedural Posture

Appeal / Court of Appeal Judgment on Appeal From High Court (tcc) Decision to Strike Out Claim

  1. 1 Whether Solaria's sub-contract constituted a 'possession' under Article 1 Protocol 1 ECHR
  2. 2 Whether the claim was statute-barred under section 7(5) of the Human Rights Act 1998
  3. 3 Whether the court should exercise its discretion to allow the claim to proceed outside the primary limitation period

Ratio Decidendi

The Court of Appeal held that Solaria's sub-contract was a possession under A1P1 despite assignment restrictions, but the claim was statute-barred as it was brought nearly five years after the relevant act, and Solaria failed to demonstrate any equitable grounds to extend the limitation period under section 7(5)(b) of the Human Rights Act 1998.

Court Disposition

Appeal dismissed

Orders

  • Claim remains struck out
  • No extension of limitation period granted