Halsion Limited v St Thomas Street Development Limited
The Particulars of Claim were so prolix, unclear, and non-compliant with CPR Part 16 and the TCC Guide that they failed to provide a concise statement of material facts, making it impossible for the defendant to respond effectively or for the court to manage the case. The claims for construction, rectification, and estoppel by convention were not properly pleaded, and the claims for declaratory relief as to the effect of the adjudications and contract construction served no useful purpose. The only proportionate and practical response was to strike out the Particulars of Claim as a whole, with permission to apply to amend subject to compliance with the rules and guidance.
- Parties
- Claimant: Halsion Limited; Defendant: St Thomas Street Development Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 11 September 2024
- Procedural Posture
- Civil (construction Dispute) / Application to Strike Out And/or for Summary Judgment on the Particulars of Claim
- Outcome
- Particulars of Claim struck out in their entirety; permission to apply to amend granted, subject to compliance with rules and guidance.
- Legal Topics
- Pleading Requirements, Rectification of Contract, Estoppel by Convention, Declaratory Relief, Interpretation of Construction Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Halsion Limited
Claimant
St Thomas Street Development Limited
Defendant
Procedural Posture
Civil (construction Dispute) / Application to Strike Out And/or for Summary Judgment on the Particulars of Claim
Legal Issues
- 1 Whether the Particulars of Claim should be struck out for non-compliance with CPR Part 16 and the TCC Guide
- 2 Whether the claims for construction, rectification, and estoppel by convention are properly pleaded
- 3 Whether declaratory relief as to the effect of adjudication decisions and contract construction should be granted
Ratio Decidendi
The Particulars of Claim were so prolix, unclear, and non-compliant with CPR Part 16 and the TCC Guide that they failed to provide a concise statement of material facts, making it impossible for the defendant to respond effectively or for the court to manage the case. The claims for construction, rectification, and estoppel by convention were not properly pleaded, and the claims for declaratory relief as to the effect of the adjudications and contract construction served no useful purpose. The only proportionate and practical response was to strike out the Particulars of Claim as a whole, with permission to apply to amend subject to compliance with the rules and guidance.
Court Disposition
Particulars of Claim struck out in their entirety; permission to apply to amend granted, subject to compliance with rules and guidance.
Orders
- The Particulars of Claim are struck out pursuant to CPR 3.4(2)(a), (b), and (c).
- Permission to apply to amend is granted, subject to the court's approval of any redrafted pleading at a consequentials hearing.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment