Aecom Design Build Ltd v Staptina Engineering Services Ltd [2017] EWHC 723 (TCC) (05 April 2017)
The adjudicator did not exceed her jurisdiction because the dispute referred included both whether deductions for defects were permitted and, if so, how such deductions should be calculated. The parties' submissions and evidence encompassed the method of calculation. There was no breach of natural justice as the relevant issues were fully canvassed and the adjudicator was entitled to reach her own conclusion on the contractual interpretation. The declarations sought by AECOM are refused and the Part 8 claim is dismissed.
- Citation
- [2017] EWHC 723 (TCC)
- Parties
- Claimant: AECOM Design Build Limited; Defendant: Staptina Engineering Services Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 05 April 2017
- Procedural Posture
- Part 8 Claim / Judgment After Hearing on Application for Declarations Regarding Adjudicator's Decision
- Outcome
- Claim dismissed
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Natural Justice in Adjudication, Interpretation of Construction Contracts, Severance of Adjudicator's Decision
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
AECOM Design Build Limited
Claimant
Staptina Engineering Services Limited
Defendant
Procedural Posture
Part 8 Claim / Judgment After Hearing on Application for Declarations Regarding Adjudicator's Decision
Legal Issues
- 1 Whether the adjudicator exceeded her jurisdiction by deciding how deductions for defects should be calculated
- 2 Whether there was a breach of natural justice in the adjudication process
- 3 Whether the impugned parts of the adjudicator's decision should be severed
Ratio Decidendi
The adjudicator did not exceed her jurisdiction because the dispute referred included both whether deductions for defects were permitted and, if so, how such deductions should be calculated. The parties' submissions and evidence encompassed the method of calculation. There was no breach of natural justice as the relevant issues were fully canvassed and the adjudicator was entitled to reach her own conclusion on the contractual interpretation. The declarations sought by AECOM are refused and the Part 8 claim is dismissed.
Court Disposition
Claim dismissed
Orders
- Declarations sought by AECOM refused
- Part 8 claim dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment