Mowlem Plc (t/a Mowlem Marine) v Stena Line Ports Ltd

Mowlem Plc (t/a Mowlem Marine) v Stena Line Ports Ltd

The parties' relationship was governed by the letter of intent dated 4 July 2003, which capped Stena's liability to pay Mowlem at £10 million for all works. There was no waiver, estoppel, or implied term permitting payment beyond this cap. No quantum meruit claim arises where a contract governs payment. The date of 18 July 2003 was not a temporal limit on the cap but an estimate of programme duration.

Parties
Claimant: Mowlem PLC (trading as Mowlem Marine); Defendant: Stena Line Ports Limited
Jurisdiction
England and Wales
Judgment Date
06 October 2004
Procedural Posture
Civil (construction/contract) / Judgment After Trial
Outcome
Claim dismissed; counterclaim allowed
Legal Topics
Letters of Intent, Quantum Meruit, Contractual Interpretation, Waiver, Estoppel

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Mowlem PLC (trading as Mowlem Marine)

Claimant

Stena Line Ports Limited

Defendant

Procedural Posture

Civil (construction/contract) / Judgment After Trial

  1. 1 Whether Mowlem is entitled to be paid a reasonable sum for works carried out beyond the limits of the final letter of intent dated 4 July 2003
  2. 2 Whether the £10 million cap in the letter of intent applies to all works, including those after 18 July 2003
  3. 3 Whether Stena waived or is estopped from relying on the £10 million cap

Ratio Decidendi

The parties' relationship was governed by the letter of intent dated 4 July 2003, which capped Stena's liability to pay Mowlem at £10 million for all works. There was no waiver, estoppel, or implied term permitting payment beyond this cap. No quantum meruit claim arises where a contract governs payment. The date of 18 July 2003 was not a temporal limit on the cap but an estimate of programme duration.

Court Disposition

Claim dismissed; counterclaim allowed

Orders

  • Declaration that Mowlem's entitlement to payment for the Works is subject to a maximum of £10 million