Costain Ltd v Tarmac Holdings Ltd [2017] EWHC 319 (TCC) (28 February 2017)

Costain Ltd v Tarmac Holdings Ltd [2017] EWHC 319 (TCC) (28 February 2017)

The sub-contract contained two sets of contract conditions: the Framework Contract (covering the quotation process) and the Supply Contract (covering the supply of concrete). Clause 93 of the Supply Contract provided a two-stage dispute resolution process (adjudication, then arbitration) for disputes arising out of...

Source-derived case information.

Citation
[2017] EWHC 319 (TCC)
Parties
Claimant: Costain Limited; Defendant: Tarmac Holdings Limited
Jurisdiction
England and Wales
Judgment Date
28 February 2017
Procedural Posture
Application to Stay Proceedings Under Arbitration Act 1996 S.9(1) / First Instance Judgment on Stay Application
Outcome
Application granted; proceedings stayed in favour of arbitration.
Legal Topics
Arbitration Agreements, Stay of Proceedings, Contract Interpretation, Adjudication, Jurisdiction Clauses
Construction Law Contract Law Arbitration Arbitration Agreements Stay of Proceedings Contract Interpretation Adjudication Jurisdiction Clauses

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 13 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Costain Limited

Claimant

Tarmac Holdings Limited

Defendant

Procedural Posture

Application to Stay Proceedings Under Arbitration Act 1996 S.9(1) / First Instance Judgment on Stay Application

  1. 1 Whether the sub-contract contained a binding arbitration agreement covering the dispute
  2. 2 Whether the claim is a matter to be referred to arbitration under the agreement
  3. 3 Whether the arbitration agreement is inoperative or null and void under s.9(4) of the Arbitration Act 1996

Ratio Decidendi

The sub-contract contained two sets of contract conditions: the Framework Contract (covering the quotation process) and the Supply Contract (covering the supply of concrete). Clause 93 of the Supply Contract provided a two-stage dispute resolution process (adjudication, then arbitration) for disputes arising out of the supply of concrete. The present dispute arose from the supply of allegedly defective concrete and thus fell within clause 93. The existence of other dispute resolution clauses in the Framework Contract did not override or render clause 93 inapplicable. The arbitration agreement was not inoperative or null and void; the parties' conduct did not amount to abandonment,...

Court Disposition

Application granted; proceedings stayed in favour of arbitration.

Orders

  • Proceedings stayed pursuant to s.9(1) Arbitration Act 1996 pending arbitration.