Bell Building Limited v TClarke Contracting Limited
The Adjudicator did not act outside his jurisdiction or breach natural justice; he responded to the parties' submissions and corrected the arithmetic based on material and arguments before him. The decision is enforceable.
- Parties
- Claimant: Bell Building Limited; Defendant: TClarke Contracting Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 30 July 2024
- Procedural Posture
- Adjudication Enforcement Proceedings / Summary Judgment Application
- Outcome
- Summary judgment granted for the Claimant; Adjudicator's decision enforced.
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Natural Justice, Payment Disputes, JCT Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Bell Building Limited
Claimant
TClarke Contracting Limited
Defendant
Procedural Posture
Adjudication Enforcement Proceedings / Summary Judgment Application
Legal Issues
- 1 Whether the Adjudicator acted outside his jurisdiction by awarding more than the sum claimed
- 2 Whether there was a breach of natural justice by the Adjudicator
- 3 Whether the Adjudicator's decision is enforceable
Ratio Decidendi
The Adjudicator did not act outside his jurisdiction or breach natural justice; he responded to the parties' submissions and corrected the arithmetic based on material and arguments before him. The decision is enforceable.
Court Disposition
Summary judgment granted for the Claimant; Adjudicator's decision enforced.
Orders
- Bell is entitled to summary judgment for £2,129,672.69 plus VAT and interest as per the Adjudicator's decision.
- Counsel to prepare a draft order; costs to be agreed or assessed summarily if not agreed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment