Greenore Port Ltd v Technical & General Guarantee Company Ltd [2006] EWHC 3119 (TCC) (30 November 2006)
SAR's contract was validly terminated under clause 63 for persistent and fundamental breach, including abandonment after loss of insurance. Claimant's rejection of defendant's offer was not unreasonable given circumstances and lack of confidence in SAR and BME. Claimant is entitled to recover under the performance bond the difference between actual completion costs and the notional final account, subject to agreed quantum. Damages for delay are recoverable per contract. No additional recovery for omitted rock dredging or loss of profits as additions and omissions approximately cancelled out.
- Citation
- [2006] EWHC 3119 (TCC)
- Parties
- Claimant: Greenore Port Ltd.; Defendant: Technical & General Guarantee Company Ltd.
- Jurisdiction
- England and Wales
- Judgment Date
- 30 November 2006
- Procedural Posture
- Commercial Construction Dispute / Final Judgment
- Outcome
- Claim allowed in part
- Legal Topics
- Performance Bonds, Contract Termination, Damages for Delay, Quantification of Loss, Repudiation, Assignment of Debts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Greenore Port Ltd.
Claimant
Technical & General Guarantee Company Ltd.
Defendant
Procedural Posture
Commercial Construction Dispute / Final Judgment
Legal Issues
- 1 Whether SAR's contract was terminated under clause 63 or repudiated
- 2 Whether claimant is precluded from recovery due to rejection of defendant's offer
- 3 Entitlement and quantification of losses under the performance bond
Ratio Decidendi
SAR's contract was validly terminated under clause 63 for persistent and fundamental breach, including abandonment after loss of insurance. Claimant's rejection of defendant's offer was not unreasonable given circumstances and lack of confidence in SAR and BME. Claimant is entitled to recover under the performance bond the difference between actual completion costs and the notional final account, subject to agreed quantum. Damages for delay are recoverable per contract. No additional recovery for omitted rock dredging or loss of profits as additions and omissions approximately cancelled out.
Court Disposition
Claim allowed in part
Orders
- Defendant to pay claimant €413,647 under performance bond
- Defendant to pay contractual damages for delay
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment