Hillcourt (Docklands) Ltd v Teliasonera AB [2006] EWHC 508 (Ch) (14 February 2006)
A stay of execution of the Section 66 judgment and related orders is granted pending trial and disposal of the consolidated actions, as TeliaSonera has raised arguable grounds for rescission based on undisclosed commission, and a stay will preserve the status quo without causing undue prejudice to Hillcourt. TeliaSonera must give a cross-undertaking in damages.
- Citation
- [2006] EWHC 508 (Ch)
- Parties
- Claimant: Hillcourt (Docklands) Ltd; Defendant: TeliaSonera AB
- Jurisdiction
- England and Wales
- Judgment Date
- 14 February 2006
- Procedural Posture
- Interlocutory Application / Application for Interim Injunction and Stay of Execution
- Outcome
- Stay of execution granted; injunction against rent review granted or substituted by undertaking; costs awarded to TeliaSonera.
- Legal Topics
- Enforcement of Arbitration Awards, Lease Rescission, Interim Injunctions, Stay of Execution, Agent Commission, Rent Review
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Hillcourt (Docklands) Ltd
Claimant
TeliaSonera AB
Defendant
Procedural Posture
Interlocutory Application / Application for Interim Injunction and Stay of Execution
Legal Issues
- 1 Whether to grant an interim injunction restraining enforcement of arbitration award and rent review
- 2 Whether to stay execution of judgment enforcing arbitration award
- 3 Whether TeliaSonera is entitled to rescind the lease due to undisclosed commission payment
Ratio Decidendi
A stay of execution of the Section 66 judgment and related orders is granted pending trial and disposal of the consolidated actions, as TeliaSonera has raised arguable grounds for rescission based on undisclosed commission, and a stay will preserve the status quo without causing undue prejudice to Hillcourt. TeliaSonera must give a cross-undertaking in damages.
Court Disposition
Stay of execution granted; injunction against rent review granted or substituted by undertaking; costs awarded to TeliaSonera.
Orders
- Stay of execution of Section 66 judgment and Deputy Master Bartlett's order of 12 August 2004 pending trial and disposal of actions.
- TeliaSonera to give cross-undertaking in damages.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment