Hillcourt (Docklands) Ltd v Teliasonera AB

Hillcourt (Docklands) Ltd v Teliasonera AB

A stay of execution of the Section 66 judgment (enforcing the arbitration award) is granted pending trial and disposal of the consolidated actions, on terms that TeliaSonera gives a cross-undertaking in damages. The court will not grant an injunction restraining enforcement but will substitute a stay. An injunction restraining Hillcourt from proceeding with a rent review is granted, or alternatively, an undertaking to cease further steps under the rent review provisions, supported by a cross-undertaking in damages from TeliaSonera.

Parties
Claimant: Hillcourt (Docklands) Ltd; Defendant: TeliaSonera AB
Jurisdiction
England and Wales
Judgment Date
14 February 2006
Procedural Posture
Civil / Interlocutory Application for Interim Injunction and Stay of Execution
Outcome
Stay of execution granted; injunction restraining rent review granted; costs awarded to TeliaSonera.
Legal Topics
Enforcement of Arbitration Awards, Stay of Execution, Injunctions, Agency and Fiduciary Duties, Rescission of Contract, Rent Review

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 3 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Hillcourt (Docklands) Ltd

Claimant

TeliaSonera AB

Defendant

Procedural Posture

Civil / Interlocutory Application for Interim Injunction and Stay of Execution

  1. 1 Whether to grant an interim injunction restraining enforcement of an arbitration award and related orders
  2. 2 Whether to stay execution of the judgment enforcing the arbitration award
  3. 3 Whether to restrain the claimant from proceeding with a rent review under the lease

Ratio Decidendi

A stay of execution of the Section 66 judgment (enforcing the arbitration award) is granted pending trial and disposal of the consolidated actions, on terms that TeliaSonera gives a cross-undertaking in damages. The court will not grant an injunction restraining enforcement but will substitute a stay. An injunction restraining Hillcourt from proceeding with a rent review is granted, or alternatively, an undertaking to cease further steps under the rent review provisions, supported by a cross-undertaking in damages from TeliaSonera.

Court Disposition

Stay of execution granted; injunction restraining rent review granted; costs awarded to TeliaSonera.

Orders

  • Stay of execution of the Section 66 judgment and order of Deputy Master Bartlett of 12 August 2004, pending trial and disposal of the actions, on terms of a cross-undertaking in damages by TeliaSonera.
  • Injunction restraining Hillcourt from proceeding with a rent review under the lease, or alternatively, an undertaking to cease further steps under the rent review provisions, supported by a cross-undertaking in damages by TeliaSonera.