Geoquip Marine Operations AG v Tower Resources Cameroon SA & Anor
Geoquip is entitled to the balance of the lumpsum contract price upon provision of a compliant preliminary report, regardless of delay, as the contract did not make timely delivery a condition precedent to payment. Standby charges are not recoverable under the contract or by estoppel, as no clear shared assumption or contractual provision supports liability. Tower plc remains liable as guarantor, as the extension contract did not discharge its obligations.
- Parties
- Claimant: Geoquip Marine Operations AG; Defendant: Tower Resources Cameroon SA; Defendant: Tower Resources PLC
- Jurisdiction
- England and Wales
- Judgment Date
- 16 March 2022
- Procedural Posture
- Commercial Contract Dispute / Final Judgment
- Outcome
- Claim for balance of contract price allowed; claim for standby costs dismissed; guarantee liability upheld.
- Legal Topics
- Contract Interpretation, Guarantee Liability, Estoppel by Convention, Estoppel by Contract, Quantum Meruit
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Geoquip Marine Operations AG
Claimant
Tower Resources Cameroon SA
Defendant
Tower Resources PLC
Defendant
Procedural Posture
Commercial Contract Dispute / Final Judgment
Legal Issues
- 1 Is Geoquip entitled to payment of the balance of the lumpsums claimed for the work done under the Contract?
- 2 Is Geoquip entitled to recovery of the Standby Costs pursuant to the terms of the Contract?
- 3 Is Geoquip entitled to recovery of the Standby Costs on the basis of estoppel by convention or contract?
Ratio Decidendi
Geoquip is entitled to the balance of the lumpsum contract price upon provision of a compliant preliminary report, regardless of delay, as the contract did not make timely delivery a condition precedent to payment. Standby charges are not recoverable under the contract or by estoppel, as no clear shared assumption or contractual provision supports liability. Tower plc remains liable as guarantor, as the extension contract did not discharge its obligations.
Court Disposition
Claim for balance of contract price allowed; claim for standby costs dismissed; guarantee liability upheld.
Orders
- Tower Resources Cameroon SA and Tower Resources PLC to pay Geoquip Marine Operations AG US$610,091.68 as balance of contract price.
- Claim for standby charges in the sum of US$1,619,541.69 dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment