McAlpine PPS Pipeline Systems Joint Venture v Transco Plc [2004] EWHC 2030 (TCC) (12 May 2004)
The adjudicator acted within his jurisdiction as the dispute referred encompassed the entitlement to interest for late certification of compensation events, and the procedure, though imperfect, did not amount to a material breach of natural justice or cause significant prejudice to Transco. The decision was responsive to the issues referred and should be enforced.
- Citation
- [2004] EWHC 2030 (TCC)
- Parties
- Claimant: McAlpine PPS Pipeline Systems Joint Venture; Defendant: Transco PLC
- Jurisdiction
- England and Wales
- Judgment Date
- 12 May 2004
- Procedural Posture
- Application to Enforce Adjudicator's Decision (cpr Part 24) / Judgment on Summary Enforcement Application
- Outcome
- application granted
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Natural Justice in Adjudication, Housing Grants, Construction and Regeneration Act 1996, Scheme for Construction Contracts 1998, Interest on Late Payments, Compensation Events Under NEC Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
McAlpine PPS Pipeline Systems Joint Venture
Claimant
Transco PLC
Defendant
Procedural Posture
Application to Enforce Adjudicator's Decision (cpr Part 24) / Judgment on Summary Enforcement Application
Legal Issues
- 1 Whether the adjudicator exceeded his jurisdiction by deciding issues not referred to him
- 2 Whether the adjudicator's procedure was unfair and prejudiced the defendant
- 3 Whether the adjudicator's decision should be enforced under CPR Part 24
Ratio Decidendi
The adjudicator acted within his jurisdiction as the dispute referred encompassed the entitlement to interest for late certification of compensation events, and the procedure, though imperfect, did not amount to a material breach of natural justice or cause significant prejudice to Transco. The decision was responsive to the issues referred and should be enforced.
Court Disposition
application granted
Orders
- The adjudicator's decision is enforced; Transco PLC to pay McAlpine PPS Pipeline Systems Joint Venture £45,194.54 (being £52,119.62 less £6,925.08 already paid)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment