Ravestein BV v Trant Engineering Ltd [2023] EWHC 11 (TCC) (09 January 2023)
The court held that the arbitrator was not obviously wrong in finding that the Claimant's email did not satisfy the requirements for a valid Notice of Dissatisfaction under NEC3 clauses W2.3(11) and W2.4(2), as it only challenged the adjudicator's jurisdiction and did not indicate an intention to refer the substantive dispute to arbitration. The court further held that the issue was not of general public importance, nor was the arbitrator's decision open to serious doubt, and it was not just and proper for the court to determine the question given the circumstances.
- Citation
- [2023] EWHC 11 (TCC)
- Parties
- Claimant: Ravestein B. V.; Defendant: Trant Engineering Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 09 January 2023
- Procedural Posture
- Application for Permission to Appeal Arbitration Award / Judgment on Application for Permission to Appeal Under Section 69 Arbitration Act 1996
- Outcome
- Permission to appeal refused; other orders sought by the Claimant refused.
- Legal Topics
- Notice of Dissatisfaction, Interpretation of Standard Form Contracts, Arbitration Act 1996 Section 69, Adjudication Under NEC3, Finality of Adjudicator's Decision
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Ravestein B. V.
Claimant
Trant Engineering Limited
Defendant
Procedural Posture
Application for Permission to Appeal Arbitration Award / Judgment on Application for Permission to Appeal Under Section 69 Arbitration Act 1996
Legal Issues
- 1 Whether the Claimant served a valid Notice of Dissatisfaction under NEC3 clauses W2.3(11) and W2.4(2)
- 2 Whether the arbitrator's decision was obviously wrong in law
- 3 Whether the question is of general public importance or open to serious doubt
Ratio Decidendi
The court held that the arbitrator was not obviously wrong in finding that the Claimant's email did not satisfy the requirements for a valid Notice of Dissatisfaction under NEC3 clauses W2.3(11) and W2.4(2), as it only challenged the adjudicator's jurisdiction and did not indicate an intention to refer the substantive dispute to arbitration. The court further held that the issue was not of general public importance, nor was the arbitrator's decision open to serious doubt, and it was not just and proper for the court to determine the question given the circumstances.
Court Disposition
Permission to appeal refused; other orders sought by the Claimant refused.
Orders
- Claimant to pay Defendant's costs summarily assessed at £20,222.37
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment