Fitzpatrick Contractors Ltd v Tyco Fire and Integrated Solutions (UK) Ltd [2008] EWHC 1301 (TCC) (13 June 2008)
A binding sub-contract was formed between Fitzpatrick and Tyco on 7 May 2002, subsequently varied by agreement at the meeting on 19 June 2002. The absence of a formal deed did not prevent contractual force, as both parties intended to create legal relations and performed the contract. The relevant terms were those sent out by Fitzpatrick on 20 June 2002, reflecting the agreed variations. The evidence did not support Tyco's assertion of a prior oral agreement on 24 April 2002; the contemporaneous documents and credible witness testimony confirmed the sequence and content of contractual agreement.
- Citation
- [2008] EWHC 1301
- Parties
- Claimant: Fitzpatrick Contractors Ltd; Defendant: Tyco Fire and Integrated Solutions (UK) Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 13 June 2008
- Procedural Posture
- Commercial Construction Contract Dispute / Judgment on Preliminary Issues
- Outcome
- Binding sub-contract found; preliminary issues determined in favour of Fitzpatrick.
- Legal Topics
- Contract Formation, Variation of Contract, Authority of Agents, Interpretation of Contractual Terms, Sub Contract Terms, Liquidated Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Fitzpatrick Contractors Ltd
Claimant
Tyco Fire and Integrated Solutions (UK) Ltd
Defendant
Procedural Posture
Commercial Construction Contract Dispute / Judgment on Preliminary Issues
Legal Issues
- 1 Whether a binding sub-contract existed between Fitzpatrick and Tyco
- 2 Whether the sub-contract was varied by subsequent agreement
- 3 Whether the absence of a formal deed prevented contractual force
Ratio Decidendi
A binding sub-contract was formed between Fitzpatrick and Tyco on 7 May 2002, subsequently varied by agreement at the meeting on 19 June 2002. The absence of a formal deed did not prevent contractual force, as both parties intended to create legal relations and performed the contract. The relevant terms were those sent out by Fitzpatrick on 20 June 2002, reflecting the agreed variations. The evidence did not support Tyco's assertion of a prior oral agreement on 24 April 2002; the contemporaneous documents and credible witness testimony confirmed the sequence and content of contractual agreement.
Court Disposition
Binding sub-contract found; preliminary issues determined in favour of Fitzpatrick.
Orders
- The relevant terms of the sub-contract are those sent out by Fitzpatrick on 20 June 2002.
- Absence of formal deed does not invalidate the contract or its variations.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment