VHE Construction Plc v. Alfred McAlpine Construction Ltd [1997] EWHC Technology 370 (14th April, 1997)
A sub-contract was completed by a telephone call between Mr. Brown and Mr. Brian Thomson in late February or early March when they agreed a reduction in the period for payment, being the last issue to be resolved between the parties, and was further agreed to by the parties by their conduct. The terms were those set out in the sub-contract order dated 9 February 1993, together with the attached documents and subsequent oral amendment regarding time for payment.
- Citation
- [1997] EWHC Technology 370
- Parties
- Plaintiff: VHE Construction plc; Defendant: McAlpine Construction Ltd
- Jurisdiction
- England and Wales
- Procedural Posture
- Civil Trial (preliminary Issue) / Judgment After Trial of Preliminary Issue
- Outcome
- It is declared that a contract existed between the parties and its terms are as set out in the judgment.
- Legal Topics
- Formation of Contract, Sub Contracts, Letters of Intent, Terms of Contract, Quantum Meruit, Payment Disputes
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
VHE Construction plc
Plaintiff
McAlpine Construction Ltd
Defendant
Procedural Posture
Civil Trial (preliminary Issue) / Judgment After Trial of Preliminary Issue
Legal Issues
- 1 Whether a contract existed between the parties
- 2 If so, what were the terms of the contract
Ratio Decidendi
A sub-contract was completed by a telephone call between Mr. Brown and Mr. Brian Thomson in late February or early March when they agreed a reduction in the period for payment, being the last issue to be resolved between the parties, and was further agreed to by the parties by their conduct. The terms were those set out in the sub-contract order dated 9 February 1993, together with the attached documents and subsequent oral amendment regarding time for payment.
Court Disposition
It is declared that a contract existed between the parties and its terms are as set out in the judgment.
Orders
- Declaration that a sub-contract was completed as described in the judgment
- Terms of the contract are as set out in the sub-contract order dated 9 February 1993, attached documents, and oral amendment regarding payment period
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment