Blackpool Borough Council v Volkerfitz Patrick Ltd & Ors [2020] EWHC 1523 (TCC) (15 June 2020)
The court held that the contractual design life obligation period for the relevant components was either 20 or 25 years, not 50 years. The cold formed components were adequate for their design life and did not require replacement. Some defects were caused or exacerbated by insufficient maintenance. The claimant was entitled to limited remedial works and not full replacement. Contribution claims against subcontractors and consultants were determined according to their contractual obligations and breaches.
- Citation
- [2020] EWHC 1523 (TCC)
- Parties
- Claimant: Blackpool Borough Council; Defendant: Volkerfitzpatrick Limited; Third Party: Range Roofing & Cladding Ltd; Fourth Party: RPS Planning & Development Ltd; Fifth Party: Caunton Engineering Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 15 June 2020
- Procedural Posture
- Construction Dispute / Final Judgment After Trial
- Outcome
- Claim partly allowed; claimant awarded damages substantially less than claimed.
- Legal Topics
- Design Life Obligations, Corrosion Protection, Remedial Works, Contract Interpretation, Contribution Claims, Maintenance Obligations
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Blackpool Borough Council
Claimant
Volkerfitzpatrick Limited
Defendant
Range Roofing & Cladding Ltd
Third Party
RPS Planning & Development Ltd
Fourth Party
Caunton Engineering Ltd
Fifth Party
Procedural Posture
Construction Dispute / Final Judgment After Trial
Legal Issues
- 1 Whether the contractual design life for various components was 50 years or less
- 2 Whether the cold formed components, roof steel components, wall cladding panels, soffit panels, wave form cladding panels, tram doors, and other defects met their contractual requirements
- 3 Whether corrosion and defects were caused by inadequate maintenance or defective design/construction
Ratio Decidendi
The court held that the contractual design life obligation period for the relevant components was either 20 or 25 years, not 50 years. The cold formed components were adequate for their design life and did not require replacement. Some defects were caused or exacerbated by insufficient maintenance. The claimant was entitled to limited remedial works and not full replacement. Contribution claims against subcontractors and consultants were determined according to their contractual obligations and breaches.
Court Disposition
Claim partly allowed; claimant awarded damages substantially less than claimed.
Orders
- Defendant to pay claimant £1,110,782.10 for remedial works and associated costs.
- Claims for full replacement of cold formed components rejected.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment