Donnelly & Ors v Weybridge Construction Ltd

Donnelly & Ors v Weybridge Construction Ltd

Claimants failed to establish damages based on flat values at completion date due to insufficient evidence; joint venture partners breached fiduciary duties by acting against the interests of the joint venture, knowingly; Weybridge did not establish entitlement to damages for loss of chance due to lack of pleading...

Source-derived case information.

Parties
Claimant: Philip Donnelly and Others; Defendant: Weybridge Construction Limited; Part 20 Claimant: Weybridge Construction Limited; Part 20 Defendants: Joseph Brohoon and Others; Part 20 Claimants (2nd Claim): Heavenly Properties Limited; Part 20 Defendant (2nd Claim): Weybridge Construction Limited
Jurisdiction
England and Wales
Judgment Date
15 June 2007
Procedural Posture
Civil / Post Trial Judgment on Reserved Issues
Outcome
Claim for damages based on flat values dismissed; breach of fiduciary duty confirmed; no damages awarded for loss of chance; no sums owed to joint venture partners.
Legal Topics
Damages Assessment, Fiduciary Duties, Joint Venture Agreements, Breach of Contract, Loss of Chance, Equitable Compensation
Contract Law Equity Property Law Damages Assessment Fiduciary Duties Joint Venture Agreements Breach of Contract Loss of Chance +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Philip Donnelly and Others

Claimant

Weybridge Construction Limited

Defendant

Weybridge Construction Limited

Part 20 Claimant

Joseph Brohoon and Others

Part 20 Defendants

Heavenly Properties Limited

Part 20 Claimants (2nd Claim)

Weybridge Construction Limited

Part 20 Defendant (2nd Claim)

Procedural Posture

Civil / Post Trial Judgment on Reserved Issues

  1. 1 Assessment of damages for breach of contract based on flat values at completion date
  2. 2 Impact of appointment of selling agents on fiduciary duties under joint venture
  3. 3 Breach of fiduciary duties by joint venture partners

Ratio Decidendi

Claimants failed to establish damages based on flat values at completion date due to insufficient evidence; joint venture partners breached fiduciary duties by acting against the interests of the joint venture, knowingly; Weybridge did not establish entitlement to damages for loss of chance due to lack of pleading and evidence; no sums owed to joint venture partners under the agreement.

Court Disposition

Claim for damages based on flat values dismissed; breach of fiduciary duty confirmed; no damages awarded for loss of chance; no sums owed to joint venture partners.

Orders

  • Claimants' claim for damages based on flat values at completion date dismissed.
  • No damages awarded to Weybridge for loss of chance.