Jockey Club Racecourse Ltd v Willmott Dixon Construction Ltd [2016] EWHC 167 (TCC) (04 February 2016)
The claimant's Part 36 offer was valid and a genuine attempt to settle. Although the discount was modest, it was not derisory. It would be unjust to award indemnity costs from 21 days after the offer due to the timing and information available, but indemnity costs are appropriate from four months after the offer, when the defendant could reasonably have assessed its position.
- Citation
- [2016] EWHC 167 (TCC)
- Parties
- Claimant: Jockey Club Racecourse Limited; Defendant: Willmott Dixon Construction Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 04 February 2016
- Procedural Posture
- Civil (construction Dispute) / Case Management Hearing on Costs Following Settlement of Liability Issues
- Outcome
- Claimant awarded costs on the standard basis up to 29 May 2015 and on the indemnity basis thereafter in relation to liability issues.
- Legal Topics
- Part 36 Offers, Indemnity Costs, Liability in Construction Contracts, Case Management
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Jockey Club Racecourse Limited
Claimant
Willmott Dixon Construction Limited
Defendant
Procedural Posture
Civil (construction Dispute) / Case Management Hearing on Costs Following Settlement of Liability Issues
Legal Issues
- 1 Whether the claimant's Part 36 offer was a valid offer within the meaning of Part 36
- 2 Whether the offer was a genuine attempt to settle liability
- 3 Whether it would be unjust to award indemnity costs to the claimant from the date of the offer
Ratio Decidendi
The claimant's Part 36 offer was valid and a genuine attempt to settle. Although the discount was modest, it was not derisory. It would be unjust to award indemnity costs from 21 days after the offer due to the timing and information available, but indemnity costs are appropriate from four months after the offer, when the defendant could reasonably have assessed its position.
Court Disposition
Claimant awarded costs on the standard basis up to 29 May 2015 and on the indemnity basis thereafter in relation to liability issues.
Orders
- Claimant to have its costs in relation to liability on the standard basis up to 29 May 2015 and thereafter on an indemnity basis.
- Issues relating to interest and other consequences of CPR 36.17 reserved for future determination.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment