Toucan Energy Holdings Ltd & Anor Wirsol Energy Ltd & Ors [2021] EWHC 895 (Comm) (14 April 2021)

Toucan Energy Holdings Ltd & Anor Wirsol Energy Ltd & Ors [2021] EWHC 895 (Comm) (14 April 2021)

The court found that the claimants succeeded in their claims for damages necessary to rectify certain defects in the solar parks and in certain warranty claims arising from the same defects, but failed in their other damages claims, including for blight and refinancing costs. The defendants' counterclaim under the...

Source-derived case information.

Citation
[2021] EWHC 895 (Comm)
Parties
Claimant: Toucan Energy Holdings Limited; Claimant: Toucan Gen Co Limited; Defendant: Wirsol Energy Limited; Defendant: Wircon UK Solar Assets GmbH; Defendant: Wircon GmbH
Jurisdiction
England and Wales
Judgment Date
14 April 2021
Procedural Posture
Commercial Court Trial (high Court, Business and Property Courts, Queen's Bench Division) / Final Judgment After Trial
Outcome
Partially in favour of defendants; claimants succeed on rectification damages for certain defects, defendants succeed on ALE Contract counterclaim (except Widehurst site).
Legal Topics
Breach of Contract, Damages, Warranties, Engineering, Procurement and Construction (epc) Contracts, Operation and Maintenance (o&m) Agreements, Asset Life Extension (ale) Contracts, Refinancing Costs, Blight, Termination of Contract, Counterclaim
Commercial Law Construction Law Contract Law Energy Law Breach of Contract Damages Warranties Engineering, Procurement and Construction (epc) Contracts +6 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 10
Sign in to unlock

Parties

Toucan Energy Holdings Limited

Claimant

Toucan Gen Co Limited

Claimant

Wirsol Energy Limited

Defendant

Wircon UK Solar Assets GmbH

Defendant

Wircon GmbH

Defendant

Procedural Posture

Commercial Court Trial (high Court, Business and Property Courts, Queen's Bench Division) / Final Judgment After Trial

  1. 1 Whether the defendants breached EPC contracts by delivering defective solar parks
  2. 2 Whether the defendants breached O&M agreements
  3. 3 Whether the defendants breached warranties under the SPAs

Ratio Decidendi

The court found that the claimants succeeded in their claims for damages necessary to rectify certain defects in the solar parks and in certain warranty claims arising from the same defects, but failed in their other damages claims, including for blight and refinancing costs. The defendants' counterclaim under the ALE Contract succeeded except in relation to the Widehurst site. The court determined that the ALE Contract conditions were satisfied or waived, entitling the defendants to payment, and that the claimants were not entitled to terminate the EPC and O&M contracts as they purported to do.

Court Disposition

Partially in favour of defendants; claimants succeed on rectification damages for certain defects, defendants succeed on ALE Contract counterclaim (except Widehurst site).

Orders

  • Claimants awarded damages for rectification of certain defects in the solar parks.
  • Defendants awarded payment under the ALE Contract except for the Widehurst site.