Cantrell & Anor v Wright & Fuller Ltd
The certificate issued on 29 March 1999 was not the Final Certificate under clause 30.8 because it was issued out of time without fulfilling mandatory conditions precedent, including the completion of the adjustment process, issue of necessary certificates regarding delay and nominated sub-contractors, and proper consultation with the claimants. The certificate was ambiguous in form and intent, did not clearly express the architect's independent opinion, and failed to comply with the contractual requirements for a Final Certificate. The arbitrator erred in law by treating the time limits as wholly directory and by relying on extrinsic documents not properly incorporated. The appeal was...
- Parties
- Claimant: B. R. Cantrell; Claimant: E. P. Cantrell; Respondent: Wright & Fuller Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 30 July 2003
- Procedural Posture
- Arbitration Appeal Under Section 69(1) Arbitration Act 1996 / Judgment on Appeal From Arbitration Award
- Outcome
- Appeal allowed; arbitration award varied
- Legal Topics
- Final Certificate Validity, Time Limits in Construction Contracts, Conclusive Evidence Clauses, Conditions Precedent, Role of Architect/certifier, Contractual Interpretation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
B. R. Cantrell
Claimant
E. P. Cantrell
Claimant
Wright & Fuller Limited
Respondent
Procedural Posture
Arbitration Appeal Under Section 69(1) Arbitration Act 1996 / Judgment on Appeal From Arbitration Award
Legal Issues
- 1 Whether the certificate issued on 29 March 1999 was validly issued in accordance with clause 30.8 of the contract conditions
- 2 Whether the certificate issued on 29 March 1999 is the final certificate for the purpose of clause 30.9 of the contract conditions
Ratio Decidendi
The certificate issued on 29 March 1999 was not the Final Certificate under clause 30.8 because it was issued out of time without fulfilling mandatory conditions precedent, including the completion of the adjustment process, issue of necessary certificates regarding delay and nominated sub-contractors, and proper consultation with the claimants. The certificate was ambiguous in form and intent, did not clearly express the architect's independent opinion, and failed to comply with the contractual requirements for a Final Certificate. The arbitrator erred in law by treating the time limits as wholly directory and by relying on extrinsic documents not properly incorporated. The appeal was...
Court Disposition
Appeal allowed; arbitration award varied
Orders
- The certificate dated 29 March 1999 is not the Final Certificate under clause 30.8 and does not have conclusive effect under clause 30.9.
- The answers to issues 1 and 2 in the arbitration are varied to negative the validity and conclusiveness of the certificate.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment