Cantrell & Anor v Wright & Fuller Ltd [2003] EWHC 1545 (TCC) (30 July 2003)
The court held that the certificate issued on 29 March 1999 was not the Final Certificate in form, substance, or intent as required by the contract. The certificate failed to comply with the mandatory requirements of the JCT contract, including proper adjustment of the contract sum, addressing defects, and adherence to procedural steps. The time limits for issuing the certificate were not strictly mandatory, but the overall failure to comply with the contract's substantive requirements rendered the certificate invalid as a Final Certificate.
- Citation
- [2003] EWHC 1545 (TCC)
- Parties
- Claimant: B. R. Cantrell; Claimant: E. P. Cantrell; Respondent: Wright & Fuller Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 30 July 2003
- Procedural Posture
- Arbitration Appeal Under Arbitration Act 1996, S.69(1) / Appeal From Arbitral Award on Preliminary Issues
- Outcome
- Appeal allowed
- Legal Topics
- Validity of Final Certificate, JCT Standard Form of Contract 1980, Conclusive Evidence Clauses, Time Limits for Certificates, Arbitration Appeals
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
B. R. Cantrell
Claimant
E. P. Cantrell
Claimant
Wright & Fuller Limited
Respondent
Procedural Posture
Arbitration Appeal Under Arbitration Act 1996, S.69(1) / Appeal From Arbitral Award on Preliminary Issues
Legal Issues
- 1 Whether the certificate issued by the architect on 29 March 1999 was validly issued in accordance with clause 30.8 of the contract conditions
- 2 Whether the certificate issued on 29 March 1999 is the final certificate for the purpose of clause 30.9 of the contract conditions
Ratio Decidendi
The court held that the certificate issued on 29 March 1999 was not the Final Certificate in form, substance, or intent as required by the contract. The certificate failed to comply with the mandatory requirements of the JCT contract, including proper adjustment of the contract sum, addressing defects, and adherence to procedural steps. The time limits for issuing the certificate were not strictly mandatory, but the overall failure to comply with the contract's substantive requirements rendered the certificate invalid as a Final Certificate.
Court Disposition
Appeal allowed
Orders
- The arbitrator's award is set aside.
- It is declared that the certificate issued on 29 March 1999 was not the Final Certificate under the contract.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment