TOP KINGS LTD VRS. SINO AFRICA DEV’T CO. LTD AND ANOTHER (LC/152/2022) [2023] GHAHC 602 (12 December 2023)
Both parties derive title from the Nungua Stool and have produced subleases with overlapping signatories. There is a genuine dispute as to entitlement, and the status quo must be maintained pending a determination on the merits. Neither party has conclusively demonstrated exclusive possession. Both parties are restrained from developing the land until a composite plan is prepared and submitted to the court.
- Citation
- [2023] GHAHC 602
- Parties
- Plaintiff/applicant: Top Kings Ltd; 1st Defendant/respondent: Sino Africa Dev’t Co. Ltd; 2nd Defendant/respondent: Lands Commission
- Court
- High Court
- Jurisdiction
- Ghana
- Judgment Date
- 12 December 2023
- Case Number
- LC/152/2022
- Procedural Posture
- Civil Land Dispute / Ruling on Interlocutory Injunction Application
- Outcome
- Motion for injunction granted in part
- Legal Topics
- Interlocutory Injunction, Title to Land, Registration of Land, Possession of Land
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Top Kings Ltd
Plaintiff/applicant
Sino Africa Dev’t Co. Ltd
1st Defendant/respondent
Lands Commission
2nd Defendant/respondent
Procedural Posture
Civil Land Dispute / Ruling on Interlocutory Injunction Application
Legal Issues
- 1 Whether the Plaintiff/Applicant is entitled to an interlocutory injunction restraining the Defendants from interfering with the disputed land pending determination of the suit
- 2 Whether the status quo should be maintained until the merits of the case are determined
Ratio Decidendi
Both parties derive title from the Nungua Stool and have produced subleases with overlapping signatories. There is a genuine dispute as to entitlement, and the status quo must be maintained pending a determination on the merits. Neither party has conclusively demonstrated exclusive possession. Both parties are restrained from developing the land until a composite plan is prepared and submitted to the court.
Court Disposition
Motion for injunction granted in part
Orders
- Both parties to submit respective site plans and survey instructions to the court registry by 3rd January 2024 for onward transmission to the Survey and Mapping Division of the Lands Commission to determine the area in dispute and ownership of structures.
- Both sides are restrained from undertaking any development on any portion of the disputed land until the composite plan is received by the court.
Full Case Text
Judgment text and source record