Agate-Mabot Company Limited v W3msys Company Limited (A2/188/21) [2025] GHADC 133 (20 March 2025)

Agate-Mabot Company Limited v W3msys Company Limited (A2/188/21) [2025] GHADC 133 (20 March 2025)

Plaintiff proved on a balance of probabilities that Defendant breached the contract by failing to deliver the agreed ERP system, entitling Plaintiff to a refund, damages, interest, and costs. Defendant's absence and failure to challenge Plaintiff's evidence resulted in the facts being deemed admitted.

Source-derived case information.

Citation
[2025] GHADC 133
Parties
Plaintiff: Agate-Mabot Company Limited; Defendant: W3MSYS Company Limited
Court
District Court
Jurisdiction
Ghana
Case Number
A2/188/21
Procedural Posture
Civil / Judgment
Outcome
Judgment for Plaintiff
Legal Topics
Breach of Contract, Damages, Refund of Payment, Award of Interest, Award of Costs
Source Language
en
Contract Law Breach of Contract Damages Refund of Payment Award of Interest Award of Costs

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 20 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Agate-Mabot Company Limited

Plaintiff

W3MSYS Company Limited

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether Defendant failed to develop the appropriate software for Plaintiff’s use per their agreed terms which amounted to a breach
  2. 2 Whether the Plaintiff is entitled to the recovery of Fifty-Three Thousand Ghana Cedis (GHC 53,000) paid by Plaintiff to Defendant for the services which Defendant failed to perform
  3. 3 Whether the Plaintiff is entitled to damages and compensation for the breach of contract by the Defendant

Ratio Decidendi

Plaintiff proved on a balance of probabilities that Defendant breached the contract by failing to deliver the agreed ERP system, entitling Plaintiff to a refund, damages, interest, and costs. Defendant's absence and failure to challenge Plaintiff's evidence resulted in the facts being deemed admitted.

Court Disposition

Judgment for Plaintiff

Orders

  • Defendant to refund Fifty-Three Thousand Ghana Cedis (GHC 53,000) to Plaintiff
  • Plaintiff awarded general damages of Eighty Thousand Ghana Cedis (GHC 80,000) for breach of contract