HENDRICKS VRS. ASADTEK ROOFING (C11/111/2024) [2025] GHACC 12 (30 April 2025)

HENDRICKS VRS. ASADTEK ROOFING (C11/111/2024) [2025] GHACC 12 (30 April 2025)

The defendant breached the contract by supplying and installing roofing sheets of a lower specification than agreed, rendering the roofs unfit for purpose. The plaintiff proved his claim on a balance of probabilities and is entitled to specific performance, damages, and costs.

Source-derived case information.

Citation
[2025] GHACC 12
Parties
Plaintiff: Ato Hendricks; Defendant: Asadtek Roofing
Court
Circuit Court
Jurisdiction
Ghana
Judgment Date
30 April 2025
Case Number
C11/111/2024
Procedural Posture
Civil / Final Judgment in Default of Appearance
Outcome
Judgment for the plaintiff in default of appearance
Legal Topics
Sale of Goods, Breach of Contract, Specific Performance, Damages, Implied Warranty, Merchantability
Source Language
english
Contract Law Commercial Law Sale of Goods Breach of Contract Specific Performance Damages Implied Warranty Merchantability

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 9 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Ato Hendricks

Plaintiff

Asadtek Roofing

Defendant

Procedural Posture

Civil / Final Judgment in Default of Appearance

  1. 1 Whether the defendant breached the contract by supplying roofing sheets not conforming to agreed specifications
  2. 2 Whether the plaintiff is entitled to specific performance and damages for breach of contract

Ratio Decidendi

The defendant breached the contract by supplying and installing roofing sheets of a lower specification than agreed, rendering the roofs unfit for purpose. The plaintiff proved his claim on a balance of probabilities and is entitled to specific performance, damages, and costs.

Court Disposition

Judgment for the plaintiff in default of appearance

Orders

  • Defendant to replace the 0.40mm pre-coated aluminium roofing sheets with 0.50mm pre-coated aluminium sheets on plaintiff’s two buildings within one month
  • Defendant to pay general damages of GH₵30,000 for breach of contract