Environmental Development Group Limited Vrs Provident Insurance Co. Ltd. [2020] GHASC 116 (18 March 2020)
The failure of the Contract Administrator to grant a reasonable extension of time constituted a fundamental breach of Clause 19, entitling the plaintiff to treat the contract as discharged and claim general damages. The plaintiff failed to strictly prove special damages and quantum meruit. The 3rd defendant's counterclaim fails as it repudiated the contract. The 1st defendant is not liable under the guarantee or performance bonds due to concurrent delay and the prevention principle.
- Citation
- Environmental Development Group Limited Vrs Provident Insurance Co. Ltd. [2020] GHASC 116 (18 March 2020)
- Parties
- Plaintiff/respondent/respondent: Environmental Development Group Limited; 1st Defendant/respondent/respondent: Provident Insurance Co. Ltd.; 2nd Defendant: Attorney General; 3rd Defendant/appellant/appellant: Ghana Education Trust Fund
- Court
- ghasc
- Jurisdiction
- Ghana
- Judgment Date
- 18 March 2020
- Procedural Posture
- Civil Appeal / Final Appellate Judgment
- Outcome
- appeal allowed in part and dismissed in part
- Legal Topics
- Breach of Contract, Extension of Time, Liquidated Damages, Quantum Meruit, Counterclaim, Performance Bond, Advance Payment Guarantee, Frustration
- Source Language
- eng
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Environmental Development Group Limited
Plaintiff/respondent/respondent
Provident Insurance Co. Ltd.
1st Defendant/respondent/respondent
Attorney General
2nd Defendant
Ghana Education Trust Fund
3rd Defendant/appellant/appellant
Procedural Posture
Civil Appeal / Final Appellate Judgment
Legal Issues
- 1 Whether the contract was still binding at the time of purported termination
- 2 Whether failure to extend time constituted a fundamental breach
- 3 Entitlement to special and general damages
Ratio Decidendi
The failure of the Contract Administrator to grant a reasonable extension of time constituted a fundamental breach of Clause 19, entitling the plaintiff to treat the contract as discharged and claim general damages. The plaintiff failed to strictly prove special damages and quantum meruit. The 3rd defendant's counterclaim fails as it repudiated the contract. The 1st defendant is not liable under the guarantee or performance bonds due to concurrent delay and the prevention principle.
Court Disposition
appeal allowed in part and dismissed in part
Orders
- Counterclaim of 3rd defendant dismissed
- Plaintiff's relief (a) granted: 1st defendant perpetually restrained from paying on guarantee bonds
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment