TSIKATA VRS TEMA DEVELOPMENT CORPORATION AND 2ORS (A11/08/19) [2024] GHACC 63 (12 February 2024)
The Plaintiff breached the lease agreement by using the land for commercial purposes without the first Defendant's approval. The Plaintiff's construction on the common boundary fence wall violated the National Building Regulations and was not authorized by the permit. The first and second Defendants trespassed onto the Plaintiff's property in their attempt to abate the breach, entitling the Plaintiff to damages for trespass. The Plaintiff failed to prove the value of items allegedly taken. The third Defendant is entitled to general damages for damage to the common boundary fence wall and electric fence caused by the Plaintiff's unauthorized construction.
- Citation
- TSIKATA VRS TEMA DEVELOPMENT CORPORATION AND 2ORS (A11/08/19) [2024] GHACC 63 (12 February 2024)
- Parties
- Plaintiff: Emmanuel Tsikata; First Defendant: Tema Development Corporation; Second Defendant: Wing Commander (Rtd) Quansah; Third Defendant: Alfonso Amorin
- Court
- ghacc
- Jurisdiction
- Ghana
- Judgment Date
- 12 February 2024
- Procedural Posture
- Civil / Judgment
- Outcome
- Judgment for all parties in part; reliefs granted and denied as specified.
- Legal Topics
- Breach of Lease Agreement, Trespass, Building Regulations, Damages, Counterclaim
- Source Language
- eng
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Emmanuel Tsikata
Plaintiff
Tema Development Corporation
First Defendant
Wing Commander (Rtd) Quansah
Second Defendant
Alfonso Amorin
Third Defendant
Procedural Posture
Civil / Judgment
Legal Issues
- 1 Whether the Plaintiff breached clause iii of the agreement with the first Defendant regarding use of land for residential purposes only
- 2 Whether the Plaintiff can use the leased plot for commercial purposes
- 3 Whether the Plaintiff's construction works violated the National Building Regulations
Ratio Decidendi
The Plaintiff breached the lease agreement by using the land for commercial purposes without the first Defendant's approval. The Plaintiff's construction on the common boundary fence wall violated the National Building Regulations and was not authorized by the permit. The first and second Defendants trespassed onto the Plaintiff's property in their attempt to abate the breach, entitling the Plaintiff to damages for trespass. The Plaintiff failed to prove the value of items allegedly taken. The third Defendant is entitled to general damages for damage to the common boundary fence wall and electric fence caused by the Plaintiff's unauthorized construction.
Court Disposition
Judgment for all parties in part; reliefs granted and denied as specified.
Orders
- First and second Defendants to restore to the Plaintiff all items taken by workers of the first Defendant, forthwith.
- GH¢1,000.00 awarded to Plaintiff against first and second Defendants as damages for trespass.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment