Okyere v NDK Financial Services Limited (CM/RPC/0455/2022) [2025] GHAHC 108 (30 May 2025)

Okyere v NDK Financial Services Limited (CM/RPC/0455/2022) [2025] GHAHC 108 (30 May 2025)

The Defendant rolled over the Plaintiff’s investments upon maturity without her authorisation, contrary to the terms of their agreement, constituting a fundamental breach of contract. The Defendant is liable to pay the Plaintiff the sum of GHS142,347.83 with interest at 20% per annum from 26th April 2021, damages...

Source-derived case information.

Citation
[2025] GHAHC 108
Parties
Plaintiff: Mrs. Winifred Okyere; Defendant: NDK Financial Services Limited
Court
High Court
Jurisdiction
Ghana
Case Number
CM/RPC/0455/2022
Procedural Posture
Civil (commercial Division) / Judgment
Outcome
Judgment for the Plaintiff
Legal Topics
Breach of Contract, Investment Disputes, Damages, Interest on Sums Due
Source Language
en
Contract Law Banking and Finance Breach of Contract Investment Disputes Damages Interest on Sums Due

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Mrs. Winifred Okyere

Plaintiff

NDK Financial Services Limited

Defendant

Procedural Posture

Civil (commercial Division) / Judgment

  1. 1 Whether the Defendant rolled over the Plaintiff’s investment upon maturity without authorisation
  2. 2 Whether the Defendant owes the Plaintiff the outstanding amount of GHS2,754.38 with interest of 16% per annum from 30th May 2021 till date of final payment
  3. 3 Whether the Defendant owes the Plaintiff the amount of GHS142,347.83 with interest of 20% per annum from 26th April 2021 till date of final payment

Ratio Decidendi

The Defendant rolled over the Plaintiff’s investments upon maturity without her authorisation, contrary to the terms of their agreement, constituting a fundamental breach of contract. The Defendant is liable to pay the Plaintiff the sum of GHS142,347.83 with interest at 20% per annum from 26th April 2021, damages for breach of contract, and costs.

Court Disposition

Judgment for the Plaintiff

Orders

  • Defendant to pay Plaintiff GHS142,347.83 with interest at 20% per annum from 26th April 2021 until final payment
  • Defendant to pay Plaintiff damages for breach of contract in the sum of GHS30,000.00