HUTCHVISION ASIA LTD v. ASIA TELEVISION LTD
The court refused to strike out ATV's defence or grant summary judgment because ATV's defences were not shown to be sham or entirely without substance and the court will not decide disputed factual issues at interlocutory stage; however the court ordered security for costs and that HAL must fortify its undertaking or ATV will be released from its undertaking, leaving disputed issues of authority and misrepresentation to trial.
- Citation
- HUTCHVISION ASIA LTD v. ASIA TELEVISION LTD
- Parties
- Plaintiff (original Action); Defendant (counterclaim): HUTCHVISION ASIA LIMITED; Defendant (original Action); Plaintiff (counterclaim): ASIA TELEVISION LIMITED; Defendant (counterclaim): LI KA SHING
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 8 September 1993
- Case Number
- HCA6757/1992
- Procedural Posture
- Civil Contract and Misrepresentation / Interlocutory Applications Following Close of Pleadings; Discovery and Inspection Completed; Applications for Strike Out, Summary Judgment, Security for Costs and Fortification of Undertaking
- Outcome
- Application by HAL to strike out ATV's defence refused; summary judgment not granted; order for security for costs granted; HAL ordered to fortify its undertaking or ATV released from its undertaking; ATV awarded costs of the interlocutory summonses (subject to further argument)
- Legal Topics
- Authority of Agent, Sham Defence/striking Out, Summary Judgment, Security for Costs, Rescission for Misrepresentation, Undertakings and Fortification
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
HUTCHVISION ASIA LIMITED
Plaintiff (original Action); Defendant (counterclaim)
ASIA TELEVISION LIMITED
Defendant (original Action); Plaintiff (counterclaim)
LI KA SHING
Defendant (counterclaim)
Procedural Posture
Civil Contract and Misrepresentation / Interlocutory Applications Following Close of Pleadings; Discovery and Inspection Completed; Applications for Strike Out, Summary Judgment, Security for Costs and Fortification of Undertaking
Legal Issues
- 1 Whether Mr Tsao had authority to bind ATV by signing the agreement
- 2 Whether ATV's defence is a sham or abuse of process warranting striking out or summary judgment
- 3 Whether alleged pre-contractual statements amounted to actionable misrepresentations relied upon by ATV
Ratio Decidendi
The court refused to strike out ATV's defence or grant summary judgment because ATV's defences were not shown to be sham or entirely without substance and the court will not decide disputed factual issues at interlocutory stage; however the court ordered security for costs and that HAL must fortify its undertaking or ATV will be released from its undertaking, leaving disputed issues of authority and misrepresentation to trial.
Court Disposition
Application by HAL to strike out ATV's defence refused; summary judgment not granted; order for security for costs granted; HAL ordered to fortify its undertaking or ATV released from its undertaking; ATV awarded costs of the interlocutory summonses (subject to further argument)
Orders
- Refuse HAL's application to strike out ATV's defence
- Refuse HAL's application for summary judgment
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment