UNISTRESS BUILDING CONSTRUCTION LTD v. TOP DOLLARS DEVELOPMENT LTD
The Bond is a double (conditional/default) bond requiring the beneficiary to prove first breach by the contractor and secondly damages to sustain a claim; Unistress has locus to apply to restrain Top Dollars because the Bond's operation is not autonomous from the underlying contract and the Contract stipulated the bond form; there are serious issues to be tried on the extent of breach and quantum of damages; the balance of convenience favours continuing the injunction pending trial. Accordingly the interlocutory injunction was continued until trial or further order and costs were ordered in the cause with certificate for two counsel.
- Citation
- UNISTRESS BUILDING CONSTRUCTION LTD v. TOP DOLLARS DEVELOPMENT LTD
- Parties
- Plaintiff / Main Contractor: Unistress; Defendant / Employer / Property Developer: Top Dollars
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 6 December 2017
- Case Number
- HCCT29/2017
- Procedural Posture
- Civil Injunction Construction Contract Dispute (performance Bond) / Interlocutory Application for Continuation of Injunction Pending Trial
- Outcome
- Injunction continued until trial or further order of the court; costs in the cause with certificate for two counsel
- Legal Topics
- Performance Bond Classification (on‑demand V Conditional), Locus Standi to Restrain Beneficiary, Architect's Certificate and Evidential Weight, Serious Issue to Be Tried, Balance of Convenience, Defects Liability
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Unistress
Plaintiff / Main Contractor
Top Dollars
Defendant / Employer / Property Developer
Procedural Posture
Civil Injunction Construction Contract Dispute (performance Bond) / Interlocutory Application for Continuation of Injunction Pending Trial
Legal Issues
- 1 Whether the Bond is a single (on demand) bond or a double (conditional/default) bond
- 2 Whether Unistress has locus standi to restrain Top Dollars from demanding or receiving payment under the Bond
- 3 Whether there is a serious issue to be tried on breach and damages
Ratio Decidendi
The Bond is a double (conditional/default) bond requiring the beneficiary to prove first breach by the contractor and secondly damages to sustain a claim; Unistress has locus to apply to restrain Top Dollars because the Bond's operation is not autonomous from the underlying contract and the Contract stipulated the bond form; there are serious issues to be tried on the extent of breach and quantum of damages; the balance of convenience favours continuing the injunction pending trial. Accordingly the interlocutory injunction was continued until trial or further order and costs were ordered in the cause with certificate for two counsel.
Court Disposition
Injunction continued until trial or further order of the court; costs in the cause with certificate for two counsel
Orders
- Continue injunction granted on 25 April 2017 and continued on 27 April 2017 until trial or further order of the court
- Costs of this application to be in the cause with certificate for two counsel
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment