CCECC (H.K.) LTD. v. MIGHT FOUNDATE DEVELOPMENT LTD.
The court refused leave to appeal under s.23, refused to remit issues under s.24 and refused removal under s.25, concluding the arbitrator's findings were not plainly wrong and fell within the presumption of finality: practical completion was validly certified on 24 June 1999; SP 8.02 does not modify Clause 23 (SP 5.03 is the amendment); the contractor was entitled to 703 days extension; time was set at large due to the respondent's non-payment; quantum determinations (including fluctuations, site overheads, interest) were within the arbitrator's fact-finding and discretionary remit; costs awarded to respondent.
- Citation
- CCECC (H.K.) LTD. v. MIGHT FOUNDATE DEVELOPMENT LTD.
- Parties
- Plaintiff / Claimant in Arbitration: CCECC (H.K.) Limited; Defendant / Respondent in Arbitration / Applicant: Might Foundate Development Limited
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 6 August 2001
- Case Number
- HCCT23/2001
- Procedural Posture
- Construction and Arbitration Proceedings / Applications for Leave to Appeal (s.23), Remission (s.24) and Removal Under S.25
- Outcome
- Applications under sections 23, 24 and 25 refused; costs awarded to respondent
- Legal Topics
- Practical Completion, Extension of Time, Time at Large, Loss and Expense, Site Overheads, Fluctuations, Interest, Remission of Awards, Leave to Appeal, Removal of Arbitrator
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
CCECC (H.K.) Limited
Plaintiff / Claimant in Arbitration
Might Foundate Development Limited
Defendant / Respondent in Arbitration / Applicant
Procedural Posture
Construction and Arbitration Proceedings / Applications for Leave to Appeal (s.23), Remission (s.24) and Removal Under S.25
Legal Issues
- 1 Whether the Practical Completion certificate of 24 June 1999 was valid
- 2 Whether notice requirements (SP 8.02/SP 5.03 and Clause 23) are conditions precedent to extensions of time
- 3 Proper method for calculating extensions of time/critical path disputes
Ratio Decidendi
The court refused leave to appeal under s.23, refused to remit issues under s.24 and refused removal under s.25, concluding the arbitrator's findings were not plainly wrong and fell within the presumption of finality: practical completion was validly certified on 24 June 1999; SP 8.02 does not modify Clause 23 (SP 5.03 is the amendment); the contractor was entitled to 703 days extension; time was set at large due to the respondent's non-payment; quantum determinations (including fluctuations, site overheads, interest) were within the arbitrator's fact-finding and discretionary remit; costs awarded to respondent.
Court Disposition
Applications under sections 23, 24 and 25 refused; costs awarded to respondent
Orders
- Refuse leave to appeal under section 23
- Refuse remission of the award under section 24
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment