HONG KONG HOUSING AUTHORITY v. WAN CHUNG CONSTRUCTION CO LTD
Leave to appeal was refused because the Arbitrator's factual findings that Wan Chung maintained a minimum site establishment due to the Authority's delay were supported by evidence (including contemporaneous daily reports, clerk of works verification and an independent surveyor's assessment), the Arbitrator applied the correct legal test for causation of prolongation costs, and the disputed issues were primarily factual such that the proposed appeal was a one-off matter not meeting the Swire test for leave.
- Citation
- HONG KONG HOUSING AUTHORITY v. WAN CHUNG CONSTRUCTION CO LTD
- Parties
- Applicant [respondent]: HONG KONG HOUSING AUTHORITY; Respondent [claimant]: WAN CHUNG CONSTRUCTION CO LTD
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 22 February 2006
- Case Number
- HCCT75/2005
- Procedural Posture
- Construction and Arbitration Proceedings Under the Arbitration Ordinance / Application for Leave to Appeal Against an Interim Arbitral Award (leave to Appeal)
- Outcome
- Leave to appeal refused
- Legal Topics
- Prolongation Costs, Concurrent Delay, Quantum of Damages, Leave to Appeal, Application of Factual Findings
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
HONG KONG HOUSING AUTHORITY
Applicant [respondent]
WAN CHUNG CONSTRUCTION CO LTD
Respondent [claimant]
Procedural Posture
Construction and Arbitration Proceedings Under the Arbitration Ordinance / Application for Leave to Appeal Against an Interim Arbitral Award (leave to Appeal)
Legal Issues
- 1 Whether the arbitrator correctly applied the test for entitlement to prolongation costs
- 2 Whether the delaying events for which the Authority was responsible were the effective or dominant cause of Wan Chung's prolongation losses
- 3 Whether the claim that a minimum site establishment was maintained due to the Authority's delay was hypothetical or supported by evidence
Ratio Decidendi
Leave to appeal was refused because the Arbitrator's factual findings that Wan Chung maintained a minimum site establishment due to the Authority's delay were supported by evidence (including contemporaneous daily reports, clerk of works verification and an independent surveyor's assessment), the Arbitrator applied the correct legal test for causation of prolongation costs, and the disputed issues were primarily factual such that the proposed appeal was a one-off matter not meeting the Swire test for leave.
Court Disposition
Leave to appeal refused
Orders
- Leave to appeal refused
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment