LAW CHI SHUN t/a TECHNICOM ENGINEERING CO v. GUARDIAN FIRE ENGINEERS & CONSULTANTS LTD
The court applied its prior findings on liability: Technicom succeeds on the unit rate issue for sprinkler heads but Guardian succeeds where duplication of claims is proved; the court adopted figures presented in closing submissions (and median figures for small disputed sums) to determine quantum without re-opening the trial. As a result the court fixed VO3A at $1,902,000, VO6 at $73,725, VO34 at $23,400, VO44 at $93,375 and adjusted the TOP1 figure to $2,949,641, and amended the summons paragraphs accordingly.
- Citation
- LAW CHI SHUN t/a TECHNICOM ENGINEERING CO v. GUARDIAN FIRE ENGINEERS & CONSULTANTS LTD
- Parties
- Plaintiff in Original Action; Defendant in Counterclaim: LAW CHI SHUN trading as TECHNICOM ENGINEERING COMPANY; Defendant in Original Action; Plaintiff in Counterclaim: GUARDIAN FIRE ENGINEERS & CONSULTANTS LIMITED
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 30 January 2004
- Case Number
- HCCT8/2000
- Procedural Posture
- Construction and Arbitration Proceedings (consolidated Hcct95/2001 & Hcct8/2000) / Decision on Quantum (post Trial)
- Outcome
- Quantum determined in accordance with the court's findings: VO3A fixed at $1,902,000; VO6 fixed at $73,725; VO34 fixed at $23,400; VO44 fixed at $93,375; TOP1 fixed at $2,949,641; summons amended; no order as to costs of this application.
- Legal Topics
- Quantum, Variation Orders, Assessment of Damages, Duplication of Claims, Unit Rates, Costs
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
LAW CHI SHUN trading as TECHNICOM ENGINEERING COMPANY
Plaintiff in Original Action; Defendant in Counterclaim
GUARDIAN FIRE ENGINEERS & CONSULTANTS LIMITED
Defendant in Original Action; Plaintiff in Counterclaim
Procedural Posture
Construction and Arbitration Proceedings (consolidated Hcct95/2001 & Hcct8/2000) / Decision on Quantum (post Trial)
Legal Issues
- 1 Appropriate unit rate for sprinkler heads ($450 v $180)
- 2 Whether Technicom duplicated claims leading to disallowance
- 3 Quantification of VO3A
Ratio Decidendi
The court applied its prior findings on liability: Technicom succeeds on the unit rate issue for sprinkler heads but Guardian succeeds where duplication of claims is proved; the court adopted figures presented in closing submissions (and median figures for small disputed sums) to determine quantum without re-opening the trial. As a result the court fixed VO3A at $1,902,000, VO6 at $73,725, VO34 at $23,400, VO44 at $93,375 and adjusted the TOP1 figure to $2,949,641, and amended the summons paragraphs accordingly.
Court Disposition
Quantum determined in accordance with the court's findings: VO3A fixed at $1,902,000; VO6 fixed at $73,725; VO34 fixed at $23,400; VO44 fixed at $93,375; TOP1 fixed at $2,949,641; summons amended; no order as to costs of this application.
Orders
- Paragraph 1 of the summons to read $2,949,641.00
- Paragraph 3 of the summons to read $2,565,221.00
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment