PENNY\'S BAY INVESTMENT CO LTD v. DIRECTOR OF LANDS

PENNY\'S BAY INVESTMENT CO LTD v. DIRECTOR OF LANDS

The Court held that compensation is calculated by reference to open market values on the date of the authorisation treating the reclamation as having occurred; subsequent events are irrelevant to that valuation and any expectations of future enhancements must be reflected in both the before and after valuations;...

Source-derived case information.

Citation
PENNY\'S BAY INVESTMENT CO LTD v. DIRECTOR OF LANDS
Parties
Applicant (respondent): Penny's Bay Investment Company Limited; Respondent (appellant): Director of Lands
Court
Court of Final Appeal
Jurisdiction
Hong Kong
Judgment Date
27 August 2010
Case Number
FACV8/2009
Procedural Posture
Final Appeal (civil) / Costs (judgment on Costs)
Outcome
Director to pay PBIL's costs of this appeal and of the appeal before the Court of Appeal.
Legal Topics
Reclamation, Injurious Affection, Statutory Compensation, Valuation Date, Subsequent Events, Costs Order, Basic Law Article 105
Source Language
en
Land Law Administrative Law Public Law Valuation Law Civil Procedure Reclamation Injurious Affection Statutory Compensation +4 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Penny's Bay Investment Company Limited

Applicant (respondent)

Director of Lands

Respondent (appellant)

Procedural Posture

Final Appeal (civil) / Costs (judgment on Costs)

  1. 1 Whether subsequent events after the date of authorisation are relevant to assessing statutory compensation
  2. 2 Proper measure of compensation: before-and-after valuation on date of authorisation
  3. 3 Whether expectations of a container terminal should be taken into account only in the after valuation

Ratio Decidendi

The Court held that compensation is calculated by reference to open market values on the date of the authorisation treating the reclamation as having occurred; subsequent events are irrelevant to that valuation and any expectations of future enhancements must be reflected in both the before and after valuations; Article 105 point was insignificant; therefore PBIL succeeded on the substantive legal issues and is entitled to costs.

Court Disposition

Director to pay PBIL's costs of this appeal and of the appeal before the Court of Appeal.

Orders

  • Director do pay PBIL's costs of this appeal and of the appeal before the Court of Appeal, including the costs of the written submissions on costs, certified fit for three counsel, to be taxed if not agreed.