W. M. CONTRACTOR LTD formerly known as W.M. FOUNDATION CO LTD v. MING LEE FOUNDATION CO LTD

W. M. CONTRACTOR LTD formerly known as W.M. FOUNDATION CO LTD v. MING LEE FOUNDATION CO LTD

The action was transferred because the issues fall within paragraph 3 of PD 6.1 and require the focused case management and early expert preparation provided by the Construction and Arbitration List; there was no justification to defer the transfer pending the Master's consideration of consolidation with HCA 1613/2019.

Citation
[2022] HKCFI 640
Parties
Plaintiff (original Action); Defendant (by Counterclaim): W. M. Contractor Limited; Defendant (original Action); Plaintiff (by Counterclaim): Ming Lee Foundation Company Limited
Court
Court of First Instance
Jurisdiction
Hong Kong
Judgment Date
3 March 2022
Case Number
HCA46/2019
Procedural Posture
Civil Construction and Arbitration (construction and Arbitration List) / Application for Transfer to Construction and Arbitration List; Decision on Transfer
Outcome
Application for transfer to the Construction and Arbitration List granted
Legal Topics
Transfer to Specialized List, Case Management, Expert Evidence, Costs
Source Language
EN

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Party arguments 2
Sign in to unlock

Parties

W. M. Contractor Limited

Plaintiff (original Action); Defendant (by Counterclaim)

Ming Lee Foundation Company Limited

Defendant (original Action); Plaintiff (by Counterclaim)

Procedural Posture

Civil Construction and Arbitration (construction and Arbitration List) / Application for Transfer to Construction and Arbitration List; Decision on Transfer

  1. 1 Whether the proceedings fall within the specialized cases described in paragraph 3 of PD 6.1 and are fit for transfer to the Construction and Arbitration List
  2. 2 Whether the court should defer the decision on transfer pending the Master's decision on consolidation with HCA 1613/2019
  3. 3 Appropriate case management directions including early identification of expert issues and preparation of concise evidence

Ratio Decidendi

The action was transferred because the issues fall within paragraph 3 of PD 6.1 and require the focused case management and early expert preparation provided by the Construction and Arbitration List; there was no justification to defer the transfer pending the Master's consideration of consolidation with HCA 1613/2019.

Court Disposition

Application for transfer to the Construction and Arbitration List granted

Orders

  • Transfer to the Construction and Arbitration List granted
  • Costs in the cause