A v. C

A v. C

The court found there was a plainly arguable prima facie arbitration agreement because the Letter of Acceptance incorporated the Plaintiff's Form of Tender (which accepted Main Contract Conditions insofar as they refer to the Subcontractor) as contract correspondence and the Main Contract definition of 'Contractor'...

Source-derived case information.

Citation
[2023] HKCFI 804
Parties
Plaintiff: A; Defendant: C
Court
Court of First Instance
Jurisdiction
Hong Kong
Judgment Date
20 March 2023
Case Number
HCCT16/2022
Procedural Posture
Construction and Arbitration (debt Claim) / Interlocutory Stay Application to Arbitrate (chambers)
Outcome
Application for stay granted
Legal Topics
Stay of Proceedings, Incorporation of Contract Terms, Arbitration Clause Operability, Nominated Sub Contracts, Costs
Source Language
en
Arbitration Construction Law Contract Law Civil Procedure Stay of Proceedings Incorporation of Contract Terms Arbitration Clause Operability Nominated Sub Contracts +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

A

Plaintiff

C

Defendant

Procedural Posture

Construction and Arbitration (debt Claim) / Interlocutory Stay Application to Arbitrate (chambers)

  1. 1 Whether an arbitration agreement existed by incorporation of Clause 41 of the Main Contract into the Subcontract
  2. 2 Whether the arbitration clause as incorporated was capable of being performed or was inoperative
  3. 3 Whether there was a prima facie case to order a stay to arbitration and leave jurisdictional questions to the tribunal

Ratio Decidendi

The court found there was a plainly arguable prima facie arbitration agreement because the Letter of Acceptance incorporated the Plaintiff's Form of Tender (which accepted Main Contract Conditions insofar as they refer to the Subcontractor) as contract correspondence and the Main Contract definition of 'Contractor' includes Nominated Domestic Sub-Contractors; parts of Clause 41 are capable of being performed or severed to give effect to the parties' intention to arbitrate; accordingly the stay to arbitration was granted and jurisdictional issues are for the arbitral tribunal to decide.

Court Disposition

Application for stay granted

Orders

  • Stay granted in terms of the Defendant's summons of 11 July 2022
  • Plaintiff to pay the costs of the application (including any reserved costs) on an indemnity basis with a certificate for counsel