On the unchallenged evidence (documentary contracts and oral testimony of the Plaintiff's representative), the court found the Defendants intended to contract; the 1st Defendant owed US$410,956.19 after credits; the 2nd Defendant gave and breached an enforceable guarantee for US$322,000; allegations of vitiating...

Source-derived case information.

Citation
[2023] HKCFI 85
Parties
Plaintiff: ACT RESOURCES INTERNATIONAL LTD.; 1st Defendant: HONG KONG ENERGY RESOURCES LIMITED; 2nd Defendant: YEUNG YUN KWONG (楊潤光)
Court
Court of First Instance
Jurisdiction
Hong Kong
Judgment Date
11 January 2023
Case Number
HCA411/2019
Procedural Posture
Contract and Debt Recovery; Guarantee and Alleged Misrepresentation / Judgment After Trial (court of First Instance)
Outcome
Judgment for the Plaintiff: (1) against the 1st Defendant in the sum of US$410,956.19 with pre-judgment interest from 14 September 2017 at HSBC prime rate plus 1% per annum and post-judgment interest until payment; (2) against the 2nd Defendant for damages of US$322,000 with pre-judgment interest from 8 May 2017 at...
Legal Topics
Guarantee, Debt Recovery, Pre Judgment and Post Judgment Interest, Vitiating Factors (fraud, Duress, Undue Influence), Counterclaim Dismissal
Source Language
en
Contract Tort Misrepresentation Restitution/unjust Enrichment Bankruptcy Civil Procedure Guarantee Debt Recovery Pre Judgment and Post Judgment Interest +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

ACT RESOURCES INTERNATIONAL LTD.

Plaintiff

HONG KONG ENERGY RESOURCES LIMITED

1st Defendant

YEUNG YUN KWONG (楊潤光)

2nd Defendant

Procedural Posture

Contract and Debt Recovery; Guarantee and Alleged Misrepresentation / Judgment After Trial (court of First Instance)

  1. 1 Whether the Defendants intended to contract with the Plaintiff despite a typographical error in the Plaintiff's name
  2. 2 Whether the 1st Defendant owes US$410,956.19 under the 4th Supplemental Contract after credits
  3. 3 Whether the 2nd Defendant guaranteed repayment of a US$322,000 loan and is in breach

Ratio Decidendi

On the unchallenged evidence (documentary contracts and oral testimony of the Plaintiff's representative), the court found the Defendants intended to contract; the 1st Defendant owed US$410,956.19 after credits; the 2nd Defendant gave and breached an enforceable guarantee for US$322,000; allegations of vitiating factors and the counterclaim failed for want of evidence; accordingly judgment was entered for the Plaintiff with interest and costs.

Court Disposition

Judgment for the Plaintiff: (1) against the 1st Defendant in the sum of US$410,956.19 with pre-judgment interest from 14 September 2017 at HSBC prime rate plus 1% per annum and post-judgment interest until payment; (2) against the 2nd Defendant for damages of US$322,000 with pre-judgment interest from 8 May 2017 at...

Orders

  • Judgment entered against HONG KONG ENERGY RESOURCES LIMITED for US$410,956.19 with pre-judgment interest from 14 September 2017 at HSBC prime +1% per annum and post-judgment interest until payment