ALPHA BUILDING CONSTRUCTION LTD v. BEST PARTNER LTD

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The application to consolidate is dismissed because the two arbitrations do not raise sufficiently common questions of fact and law to justify consolidation and because consolidation would disproportionately prolong the Sub-Contract arbitration and increase costs; issues of attribution of delay to Styletec are not material to Alpha's entitlement to an extension of time in the Main arbitration, overlapping defect claims are minor, and the Sub-Contract dispute can be resolved separately (including any architect's certificate issue).

Court disposition

Alpha's application to consolidate the Main Contract arbitration and the Sub-Contract arbitration is dismissed

Orders

  • Application to consolidate dismissed
  • Parties to be heard on costs

02

Material facts

Parties

Alpha Building Construction Ltd

Claimant (1st Arbitration); Respondent (2nd Arbitration) Counsel: Mr Geoffrey Shaw (Deacons)

Best Partner Ltd

Respondent (1st Arbitration); Employer Counsel: Mr Anthony W L Chow

Styletec Building Materials Ltd

Claimant (2nd Arbitration); Nominated Sub Contractor Counsel: Ms Eva Sit (Kao, Lee & Yip)

Amounts and remedies

  • Alpha's Total Claim: HKD 17,000,000
  • Best Partner's Total Counterclaim: HKD 5,000,000
  • Styletec's Claim for Outstanding Payment: HKD 414,000
  • Best Partner's Alleged Liquidated Damages (days): 110
  • Remaining Claim in Respect of 3 Common Items: HKD 6,000

03

Procedural history

  1. Posture

    Construction and Arbitration Proceedings (main Contract and Sub Contract Arbitrations) / Application to Consolidate Arbitrations; Pleadings Closed in Main Contract Arbitration; No Arbitrator Appointed and No Pleadings in Sub Contract Arbitration

04

Questions and positions

Legal issues

Party arguments

Applicant
Alpha applied to consolidate the Main Contract and Sub-Contract arbitrations on the basis that delay and its attribution (including alleged culpability of Styletec) and certain alleged common defects are common issues that ought to be resolved together; Alpha also seeks a declaration that Best Partner's earmarking of $414,000 is of no significance.
Respondent
Best Partner and Styletec opposed consolidation on grounds that there are insufficient common questions of fact and law, delay attribution to Styletec is irrelevant to Alpha's entitlement to an extension of time in the Main arbitration, the overlapping defects are minimal in value, the Sub-Contract claim is relatively small and can proceed promptly on documents, and consolidation would disproportionately increase costs and delay.

05

Court’s reasoning

  1. 01

    Arbitration Ordinance (Cap 341) and common law principles governing consolidation

    Consolidation of arbitrations is appropriate only where there are sufficiently common questions of fact and law and consolidation is proportionate.

  2. 02

    Terms of the Sub-Contract as pleaded in the arbitration proceedings

    Contractual preconditions in a subcontract (such as requirement for an architect's certificate) govern entitlement to delay damages under that subcontract.

  3. 03

    Court's procedural discretion and case management principles

    Court will refuse consolidation where it would unnecessarily prolong proceedings or increase costs disproportionately to the issues in the smaller arbitration.

06

Ratio, limits and disposition

Ratio decidendi

The application to consolidate is dismissed because the two arbitrations do not raise sufficiently common questions of fact and law to justify consolidation and because consolidation would disproportionately prolong the Sub-Contract arbitration and increase costs; issues of attribution of delay to Styletec are not material to Alpha's entitlement to an extension of time in the Main arbitration, overlapping defect claims are minor, and the Sub-Contract dispute can be resolved separately (including any architect's certificate issue).

Obiter and limits

  • Alpha could apply for an architect's certificate in the Sub-Contract arbitration as well as the Main Contract arbitration
  • Nine common items have been rectified by Styletec at no cost and four common items are not pursued because rectification costs are negligible
  • Some disputed items involve small repair amounts and are severable from the Main Contract dispute
  • The Sub-Contract arbitration can proceed on documents alone

Court disposition

Alpha's application to consolidate the Main Contract arbitration and the Sub-Contract arbitration is dismissed

  • Application to consolidate dismissed
  • Parties to be heard on costs

Source and reliance status

Court of First Instance · 14 May 2007

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Court of First Instance

Judgment· 14 May 2007

ALPHA BUILDING CONSTRUCTION LTD v. BEST PARTNER LTD

bjbj HCCT 80/2006

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 80 OF 2006 ____

IN THE MATTER OF ARBITRATIONS and IN THE MATTER OF THE ARBITRATION ORDINANCE (CAP 341) ____

BETWEEN ALPHA BUILDING CONSTRUCTION LTD Claimant and BEST PARTNER LTD Respondent ( 1st ARBITRATION )

AND BETWEEN STYLETEC BUILDING MATERIALS LTD Claimant and ALPHA BUILDING CONSTRUCTION LTD Respondent ( 2nd ARBITRATION ) ____ Before: Hon Reyes J in Court Date of Hearing: 14 May 2007 Date of Decision: 14 May 2007 _____

D E C I S I O N _____ I. INTRODUCTION Best Partner was the Employer, Alpha the Main Contractor, and Styletec a Nominated Sub-Contractor in the relevant project. Alpha has commenced proceedings against Best Partner under an arbitration agreement in the Main Contract. Styletec has commenced arbitration proceedings against Alpha under an arbitration agreement in the Sub-Contract. Pleadings have closed in the Main Contract arbitration. Mr. Daniel Lam has been appointed as arbitrator. Styletec has issued a Notice of Arbitration in the Sub-Contract arbitration. An arbitrator has yet to be appointed and there have not been any pleadings. Alpha has applied to consolidate both arbitrations. Best Partner and Styletec oppose consolidation. II. DISCUSSION I do not think that this is a case for consolidation. I have 2 reasons for this conclusion. First, I am not satisfied that there are sufficient common questions of fact and law in the 2 arbitrations to justify consolidation. Alpha s pleaded case in the Main Contract arbitration is that substantial completion was effected as of 12 April 2005 and practical completion took place on 7 or 8 June 2005. It claims entitlement to an extension of time from 1 April until 11 June 2005. Its total claim is for over $17 million. Alpha s claim is disputed by Best Partner which (among other things) counterclaims liquidated damages for 110 days of

delay. Best Partner s total counterclaim (including for alleged defective work by Alpha) is for over $5 million. In the Sub-Contract arbitration Styletec claims an outstanding payment of $414,000 for Kitchen Cabinet and Appliances Installation . That amount has been paid by Best Partner to Alpha and specifically earmarked by Best Partner as being payable to Styletec. It will be noticed that, as far as pleadings in the Main Contract arbitration are concerned, Alpha s case is that there has been no delay. Nonetheless, in its affidavit evidence in support of consolidation, Alpha has suggested that, if there is delay, then such delay is attributable to Styletec. No particulars of what such period of delay might be or how Styletec caused the same have been provided to me. Alpha argues that delay and its attribution will be a common theme in both arbitrations. But it seems to me Mr. Anthony Chow (appearing for Best Partner) is right. Whether or not Styletec caused delay to the Main Contract works is irrelevant to the Main Contract arbitration. Delay is only the flip side of Alpha s claim for an extension of time. The question in the Main Contract arbitration will essentially be whether Alpha is entitled to an extension of time. If it is not entitled, there will consequently be delay for which Best Partner would be entitled to damages. That would be regardless of what or who (Alpha,

Styletec or some other person) caused the delay. It is unclear on the material before me (especially in the absence of particulars of the delay allegedly caused by Styletec) that the arbitrator in the Main Contract proceedings will be concerned with who (whether Styletec or someone else) caused any delay. Indeed, even if there was delay, it does not follow that it would be attributable in whole or part to Styletec. Styletec s culpability for any delay seems to me a severable issue, which (if it is seriously alleged by Alpha) might more conveniently be dealt with in separate proceedings between Styletec and Alpha. I note that on delay there is an additional hurdle for Alpha which has been identified by Styletec. Under the Sub-Contract, Alpha is not entitled to loss or damages for delay unless the Architect has first issued a certificate stating that the Sub-Contract Works (or a section thereof) ought reasonably to have been completed within a specified period. There is no such certificate. Alpha has belatedly said that it will apply for such a certificate in the Main Contract Arbitration. But it is not apparent why such a certificate could not also be obtained in the Sub-Contract Arbitration. There are some alleged defects of which (as against Alpha) Best Partner complains in the Main Arbitration. Some of those alleged defects relate to Styletec s work. But the amount of

potential damages involved in the latter alleged common defects is minimal. I therefore do not think that the common items are a sufficient factor pointing to consolidation. Let me be more specific. Some 9 common items have been rectified by Styletec at no cost to Best Partner. Best Partner will not be claiming for those items. Some 4 common items are not being pursued by Best Partner against Alpha since the cost of rectification for these has been negligible. There is a dispute as to whether some 7 items claimed by Best Partner relate to Styletec s work at all. Alpha says yes, everyone else says . But, in any event, the amounts involved for the repair of those items (gaps under a gas heater; a telescopic box with a loose flap and another with a missing flap; and leakage from a kitchen sink, from a water outlet pipe, from a pipe inside a kitchen cabinet and from gaps in the back plate of a gas heater) cannot be significant. A remaining claim in respect of 3 common items amounts to just under $6,000. Mr. Shaw (appearing for Alpha) refers to the need for a declaration in the Main Contract arbitration that Best Partner s earmarking of the $414,000 for Styletec is of no significance. I do not see at present why this issue is a common one. It seems to me only to arise in the arbitration with Styletec. The arbitrator there is perfectly able to rule to the extent necessary on the

significance (if any) of Best Partner s earmarking. Second, I think that consolidation will unnecessarily prolong the Sub-Contract arbitration and increase its costs disproportionately. At present, only a relatively small amount is involved in the Sub-Contract Arbitration. Its outcome largely hinges on a construction of Alpha s obligations under the Sub-Contract. Best Partner has specifically paid Alpha for the $414,000 of work claimed by Styletec. It is Styletec s case that Alpha is thus under a contractual obligation to pass that amount onto Styletec. Alpha disagrees. It is accordingly possible for the Sub-Contract Arbitration to proceed on documents alone as proposed by Styletec. In the circumstances, I doubt that consolidating the Sub-Contract arbitration with the more complicated (and hence lengthier) dispute between Best Partner and Alpha would be fair. It will only increase costs and delay the time taken to arrive at a relatively straightforward decision in the Sub-Contract Arbitration. III. CONCLUSION Alpha s application to consolidate is dismissed. I shall hear the parties on costs. (A.T. Reyes) Judge of the Court of First Instance High Court Mr Geoffrey Shaw, of Messrs Deacons, for the Claimant in the 1st Arbitration and the Respondent in the 2nd Arbitration Ms Eva Sit, instructed by Messrs Kao, Lee & Yip, for the Claimant in the 2nd Arbitration Mr Anthony W L Chow, instruc 1udk 1udk

O

P

Q

R

S

T U V i$&`G hca.dot setup Microsoft Word 9.0 Judiciary Hong Kong Title Microsoft Word Document MSWordDoc Word.Document.8

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Arbitration Ordinance (Cap 341)

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.