BUILDING AUTHORITY v. GOOD FORTRESS LTD
The court was satisfied on evidence including expert affirmations and the signboard's long-term unauthorised letting that (1) notice had been validly given, (2) the signboard is "building works" erected in contravention of the Buildings Ordinance, and (3) the signboard constituted an imminent danger to life or property and alternatively was carried out with a view to letting; accordingly a Priority Demolition Order under s24B was properly granted.
- Citation
- BUILDING AUTHORITY v. GOOD FORTRESS LTD
- Parties
- Applicant: Building Authority; Interested Party: Good Fortress Limited
- Court
- District Court
- Jurisdiction
- Hong Kong
- Judgment Date
- 25 January 2017
- Case Number
- DCMP3411/2016
- Procedural Posture
- Application for Priority Demolition Order Under Section 24 B of the Buildings Ordinance (cap. 123) / Hearing and Decision (reasons Handed Down)
- Outcome
- Priority Demolition Order granted
- Legal Topics
- Priority Demolition Order, Unauthorized Building Works, Imminent Danger to Life or Property, Statutory Enforcement, Legitimate Expectation, Service of Notice
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Building Authority
Applicant
Good Fortress Limited
Interested Party
Procedural Posture
Application for Priority Demolition Order Under Section 24 B of the Buildings Ordinance (cap. 123) / Hearing and Decision (reasons Handed Down)
Legal Issues
- 1 Whether notice was given in accordance with s24B(2)-(4)
- 2 Whether the signboard constitutes "building works" and was erected in contravention of the Buildings Ordinance
- 3 Whether the signboard constitutes an imminent danger to life or property
Ratio Decidendi
The court was satisfied on evidence including expert affirmations and the signboard's long-term unauthorised letting that (1) notice had been validly given, (2) the signboard is "building works" erected in contravention of the Buildings Ordinance, and (3) the signboard constituted an imminent danger to life or property and alternatively was carried out with a view to letting; accordingly a Priority Demolition Order under s24B was properly granted.
Court Disposition
Priority Demolition Order granted
Orders
- Applicant authorized to demolish or cause to be demolished the projecting signboard attached to the external wall at 2/F to 4/F facing Argyle Street, Golden Hill Commercial Building, Nos 39-41 Argyle Street, Kowloon
- Applicant authorized to carry out or cause to be carried out such incidental works as the applicant considers necessary or expedient
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment