CHEN GUOXI v. HUMANIZED DESIGN LTD
- Citation
- [2025] HKDC 1569
- Status
- Judgment
- Jurisdiction
- Hong Kong
- Court
- District Court
- Decision
- 15 September 2025
- Posture
- Contract Renovation / Assessment of Damages After Interlocutory Judgment
- Case number
- DCCJ2048/2023
- Language
- English
More details
- Court
- District Court
- Decision
- 15 September 2025
- Posture
- Contract Renovation / Assessment of Damages After Interlocutory Judgment
- Case number
- DCCJ2048/2023
- Language
- English
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
Master accepted the unchallenged plaintiff evidence, found the defendant breached the renovation contract and awarded recoverable costs for materials and remedial completion as reasonable, allowed refund for unprovided divisible items using the applied 68.8% discount, disallowed unsupported rental claim, and entered final judgment for HK$293,521.4 plus interest and costs to be assessed.
Court disposition
Judgment for plaintiff for HK$293,521.4 with interest and costs as directed
Orders
- Defendant to pay Plaintiff HK$293,521.4
- Interest at 1% above HSBC best lending rate from 24 May 2023 to date of this assessment and thereafter at judgment rate until full payment
- Plaintiff to have costs of the action to be summarily assessed on paper; Plaintiff to file and serve Statement of Costs within 14 days; Defendant may file objections within 7 days thereafter
02
Material facts
Parties
CHEN GUOXI
PlaintiffHUMANIZED DESIGN LIMITED
DefendantAmounts and remedies
- Judgment Amount Awarded: HKD 293,521.4
- Agreed Contract Price: HKD 698,668
- Amount Paid by Plaintiff to Defendant: HKD 681,750
- Quantum Claimed in Supplemental Witness Statement: HKD 339,521.4
- Defendant Repayment Credited: HKD 8,000
- Unpaid Remainder of Contract Price Deducted: HKD 16,918
- Monthly Rental Claimed (disallowed): HKD 46,000
03
Procedural history
Posture
Contract Renovation / Assessment of Damages After Interlocutory Judgment
04
Questions and positions
Legal issues
- 01
Whether defendant breached the renovation contract by failing to complete works
- 02
Whether plaintiff is entitled to costs of completion and materials paid
- 03
Whether plaintiff may recover rental loss for delay
- 04
Whether plaintiff may recover refund for items not provided under a divisible contract
- 05
Whether plaintiff mitigated loss and calculation of quantum
Party arguments
- Applicant
- Plaintiff asserted the defendant failed to complete the contracted renovation. Plaintiff paid HK$681,750 against an agreed price of HK$698,668 and engaged a replacement contractor to finish works. Plaintiff sought HK$339,521.40 comprising materials and transportation (HK$152,133), remedial renovation (HK$164,924), rental (HK$46,000) and miscellaneous costs (HK$1,382.40), less unpaid remainder (HK$16,918) and defendant repayment (HK$8,000). Plaintiff relied on documentary and WhatsApp evidence and applied a 68.8% discount to individual items to reflect the agreed overall discount.
- Respondent
- Defendant did not appear or file a defence. Defendant made an unsolicited repayment of HK$8,000 and acknowledged liability to pay damages but raised no contested legal arguments at the assessment.
05
Court’s reasoning
Legal principles
- 01
British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co of London Ltd [1912] AC 673
Expectation damages aim to place the claimant as far as money can do in the position had the contract been performed, subject to mitigation
- 02
Hudson's Building and Engineering Contracts, 13th edition §7-040
Claimant may recover consequential losses including liabilities to third parties and additional costs of completing by another contractor
- 03
Authority applied: Chan Yee Tak Rachel v DSM Interior Design Ltd HCA 1641/2020; Prime View Inc Limited v Asian Richly Limited HCA 1672/2015 (unreported)
Where contract is divisible into separate items, claimant may claim refund for overpayment for items not provided
- 04
O35 r1 Rules of the District Court, Cap 336H
Court may proceed in defendant's absence where satisfied defendant had notice of hearing
06
Ratio, limits and disposition
Ratio decidendi
Master accepted the unchallenged plaintiff evidence, found the defendant breached the renovation contract and awarded recoverable costs for materials and remedial completion as reasonable, allowed refund for unprovided divisible items using the applied 68.8% discount, disallowed unsupported rental claim, and entered final judgment for HK$293,521.4 plus interest and costs to be assessed.
Obiter and limits
- Service of the assessment bundle to defendant's registered address was sufficient to proceed in absence
- Oral undertakings and WhatsApp exchanges can support inclusion of items the contractor ought to have quoted for
- Modest procedural costs incurred by claimant in pursuing the claim are recoverable
Court disposition
Judgment for plaintiff for HK$293,521.4 with interest and costs as directed
- Defendant to pay Plaintiff HK$293,521.4
- Interest at 1% above HSBC best lending rate from 24 May 2023 to date of this assessment and thereafter at judgment rate until full payment
- Plaintiff to have costs of the action to be summarily assessed on paper; Plaintiff to file and serve Statement of Costs within 14 days; Defendant may file objections within 7 days thereafter
Source and reliance status
District Court · 15 September 2025
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
District Court
Judgment· 15 September 2025
DCCJ 2048/2023 [2025] HKDC 1569
IN THE DISTRICT COURT OF THE
HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO 2048 OF 2023 --------------------
BETWEEN
CHEN GUOXI Plaintiff and
HUMANIZED DESIGN LIMITED Defendant -------------------- Before: Master Andrea Yu in Court Date of Hearing: 15 September 2025 Date of Assessment of Damages: 14 March 2025 ----------------------------------------
ASSESSMENT OF DAMAGES ---------------------------------------- A. Introduction This is the assessment of damages arising from a contractual claim in relation to the renovation of a residential premises. In the absence of any notice of intention to defend, Interlocutory Judgment was entered against the Defendant on 3 July 2023, with damages to be assessed. The Plaintiff is self-represented. The Defendant is absent. The Plaintiff has provided me with a receipt demonstrating he has posted the hearing bundle to the Defendant’s registered address pursuant to para. 5 of the order of Master B Mak dated 2 September 2024 (“the Order”). The Order which notifies the Defendant the date and place of the assessment of damages also appears to be served on the Defendant. I am satisfied that the Defendant has notice of this hearing. I shall proceed in the Defendant’s absence pursuant to O35, r1 of the Rules of the District Court, Cap 336H. B. Background The underlying dispute pertains to a renovation contract. The Plaintiff had engaged in the Defendant’s services for renovation of the Plaintiff’s flat. The Plaintiff and the Defendant agreed to proceed by way of a quotation signed by both parties dated 11 November 2022 (“Quotation”). The agreed cost for the renovation works to be provided by the Defendant was HK$698,668, discounted from the original quoted price of HK$1,014,950 (ie at a discount
of about 68.8%). The Plaintiff, the Defendant and“深圳雅舍家居設計家俬店”(the “Furniture Shop”) entered into a tri-partite agreement dated 6 February 2023 (“Tri-Partite Agreement”). The Plaintiff has paid the Defendant a total of HK$681,750. The renovation work began in December 2022. It transpired that the Defendant had cash flow problems and was unable to complete or substantially complete the renovation works on or before the agreed completion date of 15 March 2023. On 22 March 2023, the Plaintiff terminated the renovation contract with the Defendant. The Defendant retrieved their tools from the Property. The Defendant also acknowledged that the Defendant will pay damages for loss suffered. On 28 March 2023, the Plaintiff engaged JJ Mars Interior Design & Construction Ltd to complete the renovation work. The new contractor finished the work by Mid-May 2023. The Plaintiff and his family moved into the renovated property on 15 May 2023. On 1 February 2024, the Defendant voluntarily repaid the Plaintiff the amount of HK$8,000 as partial payment of damages. C. The Plaintiff’s Claim There appears to be some slight inconsistencies in the Plaintiff’s case against the Defendant in respect of the quantum. At the hearing before me, the Plaintiff confirmed that the correct quantum amount claimed against the Defendant is based on the amount as state in his Supplemental Witness Statement dated 29
February 2024, as being HK$339,521.40, calculated by: Materials and transportation cost incurred by the Plaintiff which under contract were the obligation of the Defendant: HK$152,133; Remedial renovation cost resulting from the Defendant’s incompletion: HK$164,924; Rental expenditure as a result of the Defendant’s delay in completion: HK$46,000; Miscellaneous costs arising from the Plaintiff’s claim: HK$1,382.40; Deducted by: Unpaid remainder of contract price: HK$16,918; The Defendant’s repayment of HK$8,000. D. Evaluation of Evidence The Plaintiff has produced substantial documentary and photographic evidence in support of his case. Having considered their contents, I give full weight to the documents adduced before me by way of documentary evidence, I find that most of the documents are inherently plausible and consistent with one another. The Plaintiff also testified at the hearing. I find the plaintiff’s oral testimony to be credible and consistent with the documentary evidence adduced in this case. The Defendant did not appear at the hearing. In such circumstances, I accept the Plaintiff’s evidence as unchallenged. E. Legal Principles Neither party in this case is legally represented. I therefore do not have the benefit of assistance from the parties on the governing legal principles. Having said that, it is trite that in the case of the defendant breaching a contract,
the plaintiff is entitled to be placed, so far as money can do, in the same position as if the contract has been performed, provided that all reasonable steps have been taken to mitigate their loss: British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co of London Ltd [1912] AC 673 at 688. The employer would be able to recover consequential loss in the shape of liabilities incurred to third parties, or loss or business or rentals, on the same principles as those in relation to defective work and delay in completion. In addition, the employer would on normal principles be entitled to other damages that result directly from the failure to complete, including most obviously the additional costs of completing by another contractor: Hudson’s Building and Engineering Contracts, 13th edition §7-040. F. Discussion Materials and transportation cost Under this heading, the Plaintiff claims for additional expenditure incurred in relation to materials and transportation costs (in respect of the custom-made furniture) which were provided under contract to be borne by the Defendant but which was ultimately borne by the Plaintiff. I have considered the same. I consider that items 1 to 24 are reasonable. As to items 25-29, the Plaintiff claims for the amounts in respect of items which were ultimately not provided by the Defendant. I note that the Quotation is
itemized with the cost item clearly set out in the next column. Given that the contract is divisible into separate items of works, it is permissible for the Plaintiff to claim for the refund of overpayment made to the Defendant: Chan Yee Tak Rachel v DSM Interior Design Ltd HCA 1641/2020 (unreported, 2 Feb 2023) at §§18-23; Prime View Inc Limited v Asian Richly Limited HCA 1672/2015 (unreported, 28 September 2017) at §§25-30. At the hearing before me, the Plaintiff has explained that he very fairly applied the 68.8% discount from the quoted charge of the item in the Quotation, reflecting the proportionate charge of the relevant items. I also accept them as reasonable. Remedial renovation cost The Plaintiff claimed that as a result of the Defendant’s failure to complete, the Plaintiff confirmed that he engaged JJ Mars Interior Design and Construction Ltd to finish the incomplete works, in the amount of HK$138,000. While items 17 to 20 are works that were not covered in the original contract, I am satisfied that the items specified therein (including installation of aircons, fans, doorbells and water heaters) are necessary and reasonable items. The Plaintiff also testified that the Defendant orally undertook and confirmed that the parties agreed that the works are all inclusive(全包). He was able to point to me Whatsapp evidence between the parties to support this. In any case,
given the description of the items, I consider that the Defendant ought to have put such items into the quotation. Item 26 is the formaldehyde application to the premises. I consider this to be necessary and reasonable. Items 27 and 29 are items which were services ultimately not provided by the Defendant but not pursued by the Plaintiff with the new contractor. By reason of the aforesaid, given the divisible nature of the contract, it is permissible for the Plaintiff to claim for the refund of overpayment made to the Defendant. Similar to the previous heading, the Plaintiff has also applied the 68.8% discount on the relevant items. I accept them as reasonable. Rental Expenditure Lastly, the Plaintiff claims for the one month rental expenditure resulting from the Defendant’s delay as his family had to stay an extra month at a different location which costs HK$46,000 per month. Recovery for this head of damages could be allowed if they are reasonably foreseeable and result from the Defendant’s failure to complete. In respect of this item, the Plaintiff was unable to give me particulars or any documentary evidence to support this claim. I am not satisfied that this item was made out and will disallow this item. Miscellaneous Items Lastly, the Plaintiff claims for the modest sum of HK$1,382.40 for costs incurred in relation to the Plaintiff’s claim against the Defendant, including
postal stamp, registration fees etc. I am satisfied that these items are reasonable and proper costs incurred as a result of the Defendant’s breach of contract. G. Conclusion In summary, the amount of damages payable by the Defendant to the Plaintiff is as follows: Adding up: Materials and Transportation Cost HK$152,133 Remedial Renovation Cost HK$164,924 Miscellaneous costs HK$1,382.4 Deducted by: Unpaid remainder of contract price HK$16,918 The Defendant’s repayment HK$8,000 Total: HK$293,521.4 H. Disposition For reasons as aforesaid, I enter a final judgment that the Defendant pay the Plaintiff the sum of HK$293,521.4, together with interests thereon at 1% above the HSBC best lending rate from the date of the Writ, 24 May 2023, to the date of this assessment and thereafter at judgment rate until full payment. The Plaintiff shall have costs of the Action, to be summarily assessed on paper. I direct that the Plaintiff should file to Court and serve on the Defendant within 14 days his Statement of Costs. The Defendant has leave to file 7 days thereafter his list of objections (if any) in relation to the Defendant’s Statement of Costs. ( Andrea Yu ) Master The Plaintiff appeared in person The Defendant was not represented and did not appear
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.