PAUL Y. - CREC ENGINEERING CO. LTD. v. AJAX PONG CONSTRUCTION LTD. AND ANOTHER
There was uncontested evidential support that servants or agents of the 1st defendant trespassed onto the site and removed hired plant and machinery contrary to contractual provisions; given the scale of the works and the risk of irreparable loss to the plaintiff, the balance of convenience favored continuing the interim injunction against the 1st defendant, while the evidence was insufficient to infer personal liability by the 2nd defendant, so the injunction against him was discharged.
- Citation
- PAUL Y. - CREC ENGINEERING CO. LTD. v. AJAX PONG CONSTRUCTION LTD. AND ANOTHER
- Parties
- Plaintiff: CREC ENGINEERING CO. LTD; 1st Defendant: AJAX PONG CONSTRUCTION LTD; 2nd Defendant: THOMAS P.S. LAU
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 5 June 2000
- Case Number
- HCA5324/2000
- Procedural Posture
- Civil Interim Injunction Arising From Subcontract Dispute / Return Date Hearing on Interim Injunction (inter Partes)
- Outcome
- Interim injunction against 1st defendant continued until trial or further order; injunction against 2nd defendant discharged.
- Legal Topics
- Interim Injunction, Trespass, Subcontract Termination, Repudiation, Balance of Convenience, Possession of Hired Plant, Director Liability
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
CREC ENGINEERING CO. LTD
Plaintiff
AJAX PONG CONSTRUCTION LTD
1st Defendant
THOMAS P.S. LAU
2nd Defendant
Procedural Posture
Civil Interim Injunction Arising From Subcontract Dispute / Return Date Hearing on Interim Injunction (inter Partes)
Legal Issues
- 1 Whether the ex parte interim injunction should be continued against the defendants
- 2 Whether the 1st defendant was responsible for blockade by independent truck drivers
- 3 Whether the 1st defendant trespassed and removed hired plant and machinery in breach of the subcontract and main contract clauses
Ratio Decidendi
There was uncontested evidential support that servants or agents of the 1st defendant trespassed onto the site and removed hired plant and machinery contrary to contractual provisions; given the scale of the works and the risk of irreparable loss to the plaintiff, the balance of convenience favored continuing the interim injunction against the 1st defendant, while the evidence was insufficient to infer personal liability by the 2nd defendant, so the injunction against him was discharged.
Court Disposition
Interim injunction against 1st defendant continued until trial or further order; injunction against 2nd defendant discharged.
Orders
- Continue interim injunction granted ex parte against AJAX PONG CONSTRUCTION LTD (1st Defendant) until trial or further order
- Discharge the interim injunction against THOMAS P.S. LAU (2nd Defendant)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment