CHEUNG SIU HO formerly t/a HANG LEE ENGINEERING CO v. PUI HING CONSTRUCTION CO LTD

CHEUNG SIU HO formerly t/a HANG LEE ENGINEERING CO v. PUI HING CONSTRUCTION CO LTD

The court found the Written Agreement (including the clause permitting deduction in special circumstances) governed the parties' liabilities; payments made by the principal contractor or insurer were nonetheless payments of the defendant's contractual funds and thus deductible under the Written Term; accordingly the defendant lawfully deducted the sum and the plaintiff's claim failed and was dismissed.

Citation
CHEUNG SIU HO formerly t/a HANG LEE ENGINEERING CO v. PUI HING CONSTRUCTION CO LTD
Parties
Plaintiff: CSH; Defendant: Defendant; Principal Contractor: Paul Y Construction Company Limited; Insurer: HIH Insurance (Asia) Ltd; Injured Employee/respondent in EC Action: Lam Chong Man
Court
District Court
Jurisdiction
Hong Kong
Judgment Date
10 July 2013
Case Number
DCCJ2198/2011
Procedural Posture
Contract Claim (sub Subcontract/deduction Dispute) / Trial / Judgment at First Instance
Outcome
Plaintiff's claim dismissed
Legal Topics
Subcontractor Liability, Deduction of Remuneration/contra Charge, Employees Compensation Payments, Limitation Period and Concealment, Completion/final Account
Source Language
EN

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 5 Authorities cited 4 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

CSH

Plaintiff

Defendant

Defendant

Paul Y Construction Company Limited

Principal Contractor

HIH Insurance (Asia) Ltd

Insurer

Lam Chong Man

Injured Employee/respondent in EC Action

Procedural Posture

Contract Claim (sub Subcontract/deduction Dispute) / Trial / Judgment at First Instance

  1. 1 Who was liable under the sub-subcontract to pay the employees compensation award?
  2. 2 If plaintiff liable, was defendant entitled to deduct the sum from plaintiff's remuneration under the sub-subcontract?
  3. 3 If not liable or deduction wrongful, whether claim barred by the Completion Agreement or by limitation/concealment rules?

Ratio Decidendi

The court found the Written Agreement (including the clause permitting deduction in special circumstances) governed the parties' liabilities; payments made by the principal contractor or insurer were nonetheless payments of the defendant's contractual funds and thus deductible under the Written Term; accordingly the defendant lawfully deducted the sum and the plaintiff's claim failed and was dismissed.

Court Disposition

Plaintiff's claim dismissed

Orders

  • Costs order nisi: plaintiff to pay defendant's costs of the action (including previously reserved costs) with counsel certificate for trial, to be taxed if not agreed
  • Costs order nisi to become absolute after 14 days unless varied within that period; plaintiff's own costs to be taxed in accordance with the Legal Aid Regulations