DECOR FLOORS ENGINEERING LTD v. WING HONG CONTRACTORS LTD AND ANOTHER
The court found that Wing Hong, by permitting and instigating Tai Fong staff and office to be held out as Wing Hong representatives (signage, name cards, organisation chart provided to ASD, and a subcontract confidentiality clause requiring Tai Fong to represent itself as agent), created ostensible authority; accordingly Wing Hong is liable to the supplier under agency by estoppel for sums due and payable, while the plaintiff's direct claims against Tai Fong were dismissed.
- Citation
- DECOR FLOORS ENGINEERING LTD v. WING HONG CONTRACTORS LTD AND ANOTHER
- Parties
- Plaintiff: D Cor Floors Engineering Limited; 1st Defendant: Wing Hong Contractors Limited; 2nd Defendant: Tai Fong Engineering Hong Kong Company Limited
- Court
- District Court
- Jurisdiction
- Hong Kong
- Judgment Date
- 17 November 2004
- Case Number
- DCCJ31/2003
- Procedural Posture
- Civil Action (goods Sold and Delivered, Contract Dispute) / Judgment After Trial
- Outcome
- Judgment for plaintiff against 1st defendant Wing Hong Contractors Limited for $296,726.00; claim against 2nd defendant Tai Fong Engineering Hong Kong Company Limited dismissed.
- Legal Topics
- Ostensible Authority, Apparent Authority, Agency by Estoppel, Goods Sold and Delivered, Offer and Acceptance, Costs
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
D Cor Floors Engineering Limited
Plaintiff
Wing Hong Contractors Limited
1st Defendant
Tai Fong Engineering Hong Kong Company Limited
2nd Defendant
Procedural Posture
Civil Action (goods Sold and Delivered, Contract Dispute) / Judgment After Trial
Legal Issues
- 1 Whether the four supply-and-lay contracts were made between plaintiff and Wing Hong
- 2 Whether the contracts were made between plaintiff and Tai Fong
- 3 Whether Tai Fong or its officer acted as agent of Wing Hong (actual or ostensible authority)
Ratio Decidendi
The court found that Wing Hong, by permitting and instigating Tai Fong staff and office to be held out as Wing Hong representatives (signage, name cards, organisation chart provided to ASD, and a subcontract confidentiality clause requiring Tai Fong to represent itself as agent), created ostensible authority; accordingly Wing Hong is liable to the supplier under agency by estoppel for sums due and payable, while the plaintiff's direct claims against Tai Fong were dismissed.
Court Disposition
Judgment for plaintiff against 1st defendant Wing Hong Contractors Limited for $296,726.00; claim against 2nd defendant Tai Fong Engineering Hong Kong Company Limited dismissed.
Orders
- Judgment for plaintiff against Wing Hong Contractors Limited in the sum of $296,726.00 with interest at prime rate plus 1% from date of the Writ to date of judgment and thereafter at the judgment rate until payment
- Claim against Tai Fong Engineering Hong Kong Company Limited dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment