CHEVALIER (ALUMINIUM ENGINEERING) HONG KONG LTD v. SUN PROPERTIES CO LTD
The Direct Payment Agreement, if any, was supplemental to and subject to the Main Contract and Sub-Contract; the Sub-Contract special provisions (notably clause 10.05 SP excluding any monetary claim for omissions and the amended clause 28 excluding additional payment for extensions of time) precluded the Contractor's claims for omitted works, abortive design costs and prolongation costs; there was no proved Agreed Final Account; consequently the Plaintiff's claims were dismissed and the Defendant's counterclaim for overpayment was allowed.
- Citation
- [2020] HKCFI 1313
- Parties
- Plaintiff / Contractor: Chevalier (Aluminium Engineering) Hong Kong Limited; Defendant / Owner: Sun Properties Company Limited
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 29 June 2020
- Case Number
- HCCT63/2017
- Procedural Posture
- Construction and Arbitration Proceedings / Judgment (court of First Instance)
- Outcome
- Plaintiff's claims dismissed; Defendant's counterclaim for overpayment allowed.
- Legal Topics
- Direct Payment Agreement, Sub Contract Terms, Variations, Final Account, Omitted Works, Prolongation Costs, Non Prevention Principle, Contract Interpretation, Overpayment/counterclaim
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Chevalier (Aluminium Engineering) Hong Kong Limited
Plaintiff / Contractor
Sun Properties Company Limited
Defendant / Owner
Procedural Posture
Construction and Arbitration Proceedings / Judgment (court of First Instance)
Legal Issues
- 1 Existence and terms of the alleged Direct Payment Agreement
- 2 Whether Contractor entitled to payments under Direct Payment Agreement or Sub-Contract
- 3 Application and effect of clause 10.05 of the Special Provisions and clause 13.4 of the General Conditions to omitted works
Ratio Decidendi
The Direct Payment Agreement, if any, was supplemental to and subject to the Main Contract and Sub-Contract; the Sub-Contract special provisions (notably clause 10.05 SP excluding any monetary claim for omissions and the amended clause 28 excluding additional payment for extensions of time) precluded the Contractor's claims for omitted works, abortive design costs and prolongation costs; there was no proved Agreed Final Account; consequently the Plaintiff's claims were dismissed and the Defendant's counterclaim for overpayment was allowed.
Court Disposition
Plaintiff's claims dismissed; Defendant's counterclaim for overpayment allowed.
Orders
- Plaintiff's claims dismissed in full.
- Counterclaim allowed: Defendant awarded recovery of overpayment in the sum of $1,509,313.17.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment