LEIGHTON CONTRACTORS (ASIA) LTD v. STELUX HOLDINGS LTD
Leave to appeal is refused because the Arbitrator was not shown to be obviously or seriously wrong: clause 23 is to be applied by reference to the state of the works at the time information was required so a causal link to likely delay must be shown; on the Arbitrator's findings the late information could not have caused delay; the Arbitrator was entitled to prefer one expert's time-slice analysis over another and did not commit technical misconduct by declining further submissions.
- Citation
- LEIGHTON CONTRACTORS (ASIA) LTD v. STELUX HOLDINGS LTD
- Parties
- Applicant (main Contractor): Leighton Contractors (Asia) Limited; Respondent (employer): Stelux Holdings Limited
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 10 September 2004
- Case Number
- HCCT29/2004
- Procedural Posture
- Arbitration and Construction Dispute (interim Arbitral Award) / Application for Leave to Appeal Against Interim Award and Alternative Application to Set Aside Award/remove Arbitrator
- Outcome
- Leave to appeal refused; application to set aside the interim award and to remove the Arbitrator dismissed.
- Legal Topics
- Extension of Time, Standard Form Contract Interpretation, Time Slice Delay Analysis, Leave to Appeal From Arbitration Award, Procedural Fairness/technical Misconduct, Expert Evidence Assessment
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Leighton Contractors (Asia) Limited
Applicant (main Contractor)
Stelux Holdings Limited
Respondent (employer)
Procedural Posture
Arbitration and Construction Dispute (interim Arbitral Award) / Application for Leave to Appeal Against Interim Award and Alternative Application to Set Aside Award/remove Arbitrator
Legal Issues
- 1 Whether clause 23 of the standard form contract entitles contractor to extension of time where an event was only 'likely to cause delay' even if no actual delay occurred
- 2 Whether the arbitrator failed to consider 'likely delay' as opposed to actual delay
- 3 Whether the arbitrator improperly rejected parties' experts and substituted her own approach without giving parties an opportunity to be heard (technical misconduct)
Ratio Decidendi
Leave to appeal is refused because the Arbitrator was not shown to be obviously or seriously wrong: clause 23 is to be applied by reference to the state of the works at the time information was required so a causal link to likely delay must be shown; on the Arbitrator's findings the late information could not have caused delay; the Arbitrator was entitled to prefer one expert's time-slice analysis over another and did not commit technical misconduct by declining further submissions.
Court Disposition
Leave to appeal refused; application to set aside the interim award and to remove the Arbitrator dismissed.
Orders
- Order nisi that Stelux is to have the costs of Leighton's leave application, such costs to be taxed if not agreed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment