FALCON CONSTRUCTION ENGINEERING LTD v. KIRIN CIVIL ENGINEERING CONTRACTORS LTD
Falcon contracted to install H‑piles within a 75 mm tolerance and was liable when deviations were established; Kirin proved deviation and recoverable losses limited to direct and foreseeable costs (Maunsell design fee and assessed additional building costs) totalling HKD 760,000; Falcon was not liable for alleged delay because completion was within a reasonable time.
- Citation
- FALCON CONSTRUCTION ENGINEERING LTD v. KIRIN CIVIL ENGINEERING CONTRACTORS LTD
- Parties
- Plaintiff: Falcon Construction Engineering Limited; Defendant / Counterclaimant: Kirin Civil Engineering Contractors Limited
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 16 November 2004
- Case Number
- HCCT11/2003
- Procedural Posture
- Construction and Arbitration Proceedings (subcontract Dispute) / Judgment (trial)
- Outcome
- Kirin's counterclaim allowed in part; Falcon's remaining claim dismissed; stay of execution lifted.
- Legal Topics
- Sub‑contracting, Pile Deviation, Site Setting Out and Survey, Extension of Time / Delay, Final Account / Settlement, Remoteness of Damages, Quantification of Loss
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Falcon Construction Engineering Limited
Plaintiff
Kirin Civil Engineering Contractors Limited
Defendant / Counterclaimant
Procedural Posture
Construction and Arbitration Proceedings (subcontract Dispute) / Judgment (trial)
Legal Issues
- 1 Whether Falcon was liable for piles deviating beyond contractual tolerance
- 2 Whether Falcon was liable for 63 days delay and attendant damages
- 3 Whether the 5 October 2000 'Final Agreement' precluded claims for pile deviation or delay
Ratio Decidendi
Falcon contracted to install H‑piles within a 75 mm tolerance and was liable when deviations were established; Kirin proved deviation and recoverable losses limited to direct and foreseeable costs (Maunsell design fee and assessed additional building costs) totalling HKD 760,000; Falcon was not liable for alleged delay because completion was within a reasonable time.
Court Disposition
Kirin's counterclaim allowed in part; Falcon's remaining claim dismissed; stay of execution lifted.
Orders
- Kirin awarded damages of HKD 760000 for pile deviation
- Falcon's remaining claim dismissed and interim judgment of 19 February 2002 remains as to amount previously awarded
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment