FALCON CONSTRUCTION ENGINEERING LTD v. KIRIN CIVIL ENGINEERING CONTRACTORS LTD

FALCON CONSTRUCTION ENGINEERING LTD v. KIRIN CIVIL ENGINEERING CONTRACTORS LTD

Falcon contracted to install H‑piles within a 75 mm tolerance and was liable when deviations were established; Kirin proved deviation and recoverable losses limited to direct and foreseeable costs (Maunsell design fee and assessed additional building costs) totalling HKD 760,000; Falcon was not liable for alleged delay because completion was within a reasonable time.

Citation
FALCON CONSTRUCTION ENGINEERING LTD v. KIRIN CIVIL ENGINEERING CONTRACTORS LTD
Parties
Plaintiff: Falcon Construction Engineering Limited; Defendant / Counterclaimant: Kirin Civil Engineering Contractors Limited
Court
Court of First Instance
Jurisdiction
Hong Kong
Judgment Date
16 November 2004
Case Number
HCCT11/2003
Procedural Posture
Construction and Arbitration Proceedings (subcontract Dispute) / Judgment (trial)
Outcome
Kirin's counterclaim allowed in part; Falcon's remaining claim dismissed; stay of execution lifted.
Legal Topics
Sub‑contracting, Pile Deviation, Site Setting Out and Survey, Extension of Time / Delay, Final Account / Settlement, Remoteness of Damages, Quantification of Loss
Source Language
EN

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Falcon Construction Engineering Limited

Plaintiff

Kirin Civil Engineering Contractors Limited

Defendant / Counterclaimant

Procedural Posture

Construction and Arbitration Proceedings (subcontract Dispute) / Judgment (trial)

  1. 1 Whether Falcon was liable for piles deviating beyond contractual tolerance
  2. 2 Whether Falcon was liable for 63 days delay and attendant damages
  3. 3 Whether the 5 October 2000 'Final Agreement' precluded claims for pile deviation or delay

Ratio Decidendi

Falcon contracted to install H‑piles within a 75 mm tolerance and was liable when deviations were established; Kirin proved deviation and recoverable losses limited to direct and foreseeable costs (Maunsell design fee and assessed additional building costs) totalling HKD 760,000; Falcon was not liable for alleged delay because completion was within a reasonable time.

Court Disposition

Kirin's counterclaim allowed in part; Falcon's remaining claim dismissed; stay of execution lifted.

Orders

  • Kirin awarded damages of HKD 760000 for pile deviation
  • Falcon's remaining claim dismissed and interim judgment of 19 February 2002 remains as to amount previously awarded