OTIS ELEVATOR CO (HK) LTD v. WIDE PROJECT ENGINEERING & CONSTRUCTION CO LTD

OTIS ELEVATOR CO (HK) LTD v. WIDE PROJECT ENGINEERING & CONSTRUCTION CO LTD

Clause 5(b) of the Sub-Contract unconditionally required the Main Contractor to pay the full value of loss by fire calculated under the contract and this obligation was not displaced by the Sub-Contractor's short-term insurance obligations in the General Specifications; the Sub-Contractor's insurance was not held...

Source-derived case information.

Citation
OTIS ELEVATOR CO (HK) LTD v. WIDE PROJECT ENGINEERING & CONSTRUCTION CO LTD
Parties
Plaintiff / Sub Contractor: Otis Elevator Company (HK) Limited; Defendant / Main Contractor: Wide Project Engineering & Construction Company Limited
Court
Court of First Instance
Jurisdiction
Hong Kong
Judgment Date
6 May 1985
Case Number
HCA15214/1983
Procedural Posture
Construction and Contract Dispute (sub Contract) / Judgment (high Court Trial)
Outcome
Judgment for plaintiff for $274,607.49 with interest at 12% per annum from date of writ to date of judgment; defendant's counterclaim dismissed.
Legal Topics
Insurance Obligations, Risk Allocation, Contract Interpretation, Privity of Insurance, Sub Contract Conditions
Source Language
en
Contract Law Insurance Law Construction Law Insurance Obligations Risk Allocation Contract Interpretation Privity of Insurance Sub Contract Conditions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Otis Elevator Company (HK) Limited

Plaintiff / Sub Contractor

Wide Project Engineering & Construction Company Limited

Defendant / Main Contractor

Procedural Posture

Construction and Contract Dispute (sub Contract) / Judgment (high Court Trial)

  1. 1 Whether the Main Contractor was liable to pay full value of fire loss under Clause 5(b) of the Sub-Contract notwithstanding insurance arrangements
  2. 2 Whether the Sub-Contractor's all risks policy and/or insurance proceeds were held for the benefit of the Main Contractor
  3. 3 Whether the Sub-Contractor was contractually obliged to insure against fire for two weeks after delivery in a manner that displaced the Main Contractor's obligation

Ratio Decidendi

Clause 5(b) of the Sub-Contract unconditionally required the Main Contractor to pay the full value of loss by fire calculated under the contract and this obligation was not displaced by the Sub-Contractor's short-term insurance obligations in the General Specifications; the Sub-Contractor's insurance was not held for the Main Contractor's benefit and the defendant's counterclaim failed.

Court Disposition

Judgment for plaintiff for $274,607.49 with interest at 12% per annum from date of writ to date of judgment; defendant's counterclaim dismissed.

Orders

  • Defendant to pay plaintiff $274,607.49 for the fire loss
  • Interest on that sum at 12% per annum from date of writ to date of judgment