KING SHING ENGINEERING (HK) CO LTD v. VINSON ENGINEERING LTD
The court held that practical site conduct constituted a waiver of strict written site-instruction requirements under the subcontract so that Kin Shing was authorised to carry out variations; the change from concealed to surface conduits was a substantial variation; valuation of variations was adopted largely on the plaintiff's QS (Mr Wong) producing total variation value $7,129,899.90; after receipts and deductions Vinson owes Kin Shing HKD 1,258,840.80; Kin Shing's departure was at Vinson's direction so no repudiatory breach and Vinson's counterclaim fails.
- Citation
- KING SHING ENGINEERING (HK) CO LTD v. VINSON ENGINEERING LTD
- Parties
- Plaintiff: KING SHING ENGINEERING (H.K.) CO., LTD.; Defendant: VINSON ENGINEERING LTD.
- Court
- Court of First Instance
- Jurisdiction
- Hong Kong
- Judgment Date
- 25 May 2006
- Case Number
- HCCT108/2003
- Procedural Posture
- Construction and Arbitration Proceedings / Judgment
- Outcome
- Judgment for Plaintiff KING SHING ENGINEERING (H.K.) CO., LTD. in the sum of HKD 1,258,840.80; Defendant VINSON ENGINEERING LTD.'s counterclaim dismissed; costs to Plaintiff (order nisi).
- Legal Topics
- Variation of Contract, Site Instructions, Payment and Interim Payments, Valuation of Variations, Repudiation and Termination, Costs and Interest
- Source Language
- EN
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
KING SHING ENGINEERING (H.K.) CO., LTD.
Plaintiff
VINSON ENGINEERING LTD.
Defendant
Procedural Posture
Construction and Arbitration Proceedings / Judgment
Legal Issues
- 1 What constituted the sub-contract and its variation procedures
- 2 Whether oral/site instructions amounted to authorisation for variations despite General Condition 3.2
- 3 Whether change from concealed to surface conduits was a contract variation
Ratio Decidendi
The court held that practical site conduct constituted a waiver of strict written site-instruction requirements under the subcontract so that Kin Shing was authorised to carry out variations; the change from concealed to surface conduits was a substantial variation; valuation of variations was adopted largely on the plaintiff's QS (Mr Wong) producing total variation value $7,129,899.90; after receipts and deductions Vinson owes Kin Shing HKD 1,258,840.80; Kin Shing's departure was at Vinson's direction so no repudiatory breach and Vinson's counterclaim fails.
Court Disposition
Judgment for Plaintiff KING SHING ENGINEERING (H.K.) CO., LTD. in the sum of HKD 1,258,840.80; Defendant VINSON ENGINEERING LTD.'s counterclaim dismissed; costs to Plaintiff (order nisi).
Orders
- Judgment for plaintiff in the amount of HKD 1,258,840.80
- Interest on HKD 1,258,840.80 from 22 December 2003 until date of judgment at 1% over Hong Kong prime, thereafter interest at judgment rate
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment